BLD-Final | 4/6/2015 | 4/7/2015 | 4/7/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Barber
|
DOC - Permit Finaled | 4/7/2015 | 4/7/2015 | 4/7/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 4/3/2015 | 4/3/2015 | 4/3/2015 | P | NR |
Jim Sly
|
|
|
The only note to add is that the permit was changed to a shell permit and not the whole building. I think this was already changed in the system by Carl who is aware of the different contractor for the interior of the building. Phone #: ###-#### Inspection requested via web by Jeremy Bar Complete all required final inspections prior to calling for Structural final.
|
BLD-Conference | 2/4/2015 | 2/5/2015 | 2/5/2015 | A | PASS |
Mike Jordan
|
|
|
Darin Phone #: ###-####
|
BLD-Framing/Rough-in | 2/5/2015 | 2/5/2015 | 2/5/2015 | A | PASS |
Mike Jordan
|
|
|
Darin Phone #: ###-####. Exterior steel stud framed walls, Structural steel. Also reviewed all special inspection reports to date.
|
BLD-Foundation | 12/12/2014 | 12/15/2014 | 12/15/2014 | A | DEFR |
Mike Jordan
|
|
|
Darren-pour time 10:00 Phone #: ###-####. Special inspectoron site.
|
BLD-Footing | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Mike Jordan
|
|
|
Aaron-please call 30 minutes prior to meet Phone #: ###-####
|