BLD-Final | 12/18/2014 | 12/18/2014 | 12/18/2014 | P | CANC |
Mike Jordan
|
|
|
Keith Phone #: ###-####
|
BLD-Final | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Mike Jordan
|
|
|
call from keith to change time//keith Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 12/8/2014 | 12/11/2014 | 12/12/2014 | A | PART |
Craig D. Hanson
|
|
|
3 exit signs need added. 1 in back middle of sales floor and one on each side of front of sales floor
|
BLD-Ceiling Grid Inspection | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Mike Jordan
|
|
|
Keith Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/3/2014 | 12/4/2014 | 12/4/2014 | A | NR |
Mike Jordan
|
|
|
Keith Phone #: ###-####
|
BLD-Conference | 11/10/2014 | 11/12/2014 | 11/12/2014 | A | CANC |
Mike Jordan
|
|
|
keith Phone #: ###-####
|
FIRE-Conference | 10/7/2014 | 10/8/2014 | 10/8/2014 | A | DONE |
Troy Cobbley
|
|
|
I verified that the insulation was being installed in the entire space for the overbuild where the anti-freeze system has been removed and fire stopped to less that 1,000 cublc feet per compartment. Keith Phone #: ###-####
|
FIRE-Conference | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | DONE |
Troy Cobbley
|
|
|
Keith and I verified the overbuild where the anti-freeze system was removed is now compartmentized to individual areas less than 1,000 cubic feet. Will need to re-inspect when filled with insulation.
|
BLD-Framing/Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | PART |
Mike Jordan
|
|
|
Keith Phone #: ###-####. Hardlids for restrooms , corridor and office, need detaild from architect. Towers at front entry.
|
BLD-Energy code compliance | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Mike Jordan
|
|
|
Keith Phone #: ###-####. Exterior furred out walls ok.
|
BLD-Framing/Rough-in | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PART |
Mike Jordan
|
|
|
Keith Phone #: ###-####. interior steel stud framed walls ok, pending electrical rough in inspection.
|
BLD-Footing | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | PART |
Mike Jordan
|
|
|
Keith-would like late AM if possible Phone #: ###-####. Work in progress on column pad footings in front of store for new facade and canopy. Will have special inspection.
|