Permit Information
Permit NumberBLD14-02182
StatusFinaled
Name WESTMINSTER II
Site Address 1259 E HEARTHSTONE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
***Plan Modification adding 280 sq. ft. rear patio*** WUI Zone A, Class A Roof, Permit for the construction of a new 4,086 sq. ft., two story (first story 2,508 sq. ft., second story 1,578 sq. ft.) single family dwelling with 5 bedrooms, 3.5 bathrooms, approximately 297 sq. ft. of covered patio/porch and a 1,089 sq. ft. attached garage per the approved plans, Rescheck, plan review report and any notations. R-1B zoning and setbacks per planning. JG A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection1/15/20161/15/20161/17/2016 DONE
DetailsTony Young
BLD-Aging Inspection1/14/20161/14/20161/15/2016 DONE
DetailsTony Young
DOC - Permit Finaled1/15/20161/15/20161/15/2016PPASS
DetailsTony Young
done
BLD-Final9/1/20159/2/20159/2/2015APASS
DetailsJim Sly
JOSH Phone #: ###-####
OK per 415.
BLD-Final8/31/20159/1/20159/1/2015ANR
DetailsTony Young
Josh Phone #: ###-####
BLD-Final8/28/20158/31/20158/31/2015ANR
DetailsTony Young
Josh Phone #: ###-####,, need engineering on glass guardrail,, hillside final,, roof soffit vents
BLD-Framing/Rough-in4/23/20154/24/20154/24/2015APASS
DetailsTony Young
Josh Phone #: ###-####,, patio frame ok,, soffit ok
BLD-Other4/2/20154/3/20154/3/2015PPASS
DetailsTony Young
soffit/// Josh Phone #: ###-####
BLD-Wall Bracing4/1/20154/2/20154/2/2015PPASS
DetailsTony Young
Shear // Josh Phone #: ###-####,, shear ok
BLD-Wall Bracing4/1/20154/2/20154/2/2015AFAIL
DetailsJim Storey
Josh Phone #: ###-#### #7 c/n ceilling covered/ plm drain line in soffit not allowed
BLD-Energy code compliance3/26/20153/26/20153/26/2015PPART
DetailsTony Young
Josh// please call 30min before- inspecting sheet rock in the eaves Phone #: ###-####,, see notes on frame inspection,, energy code ok so far
BLD-Framing/Rough-in3/26/20153/26/20153/26/2015PPART
DetailsTony Young
Josh// please call 30min before Phone #: ###-####,, ok to sheet rock after sealing up the draft stops,, need to finish correction notice,, soffits need double layer in can light boxes and fire caulked,, plan mod for added porch in review?,, also took out closet in basement room without window well,, still pending plan mod approval on those 2 items
BLD-Framing/Rough-in3/11/20153/12/20153/12/2015PFAIL
DetailsTony Young
Josh Phone #: ###-####,, correction notice posted
BLD-Wall Bracing2/18/20152/19/20152/19/2015APASS
DetailsTony Young
Josh Phone #: ###-####
BLD-Foundation1/20/20151/20/20151/20/2015PPASS
DetailsTony Young
Adam Phone #: ###-####
BLD-Footing1/14/20151/15/20151/15/2015APART
DetailsTony Young
Adam Phone #: ###-####,, lower ftgs ok
BLD-Footing1/14/20151/14/20151/14/2015PPART
DetailsTony Young
Adam Phone #: ###-####,, getting forms in place
BLD-Foundation12/11/201412/11/201412/11/2014PPART
DetailsTony Young
Adam Phone #: ###-####,, tall walls,, work in progress
BLD-Footing12/9/201412/9/201412/9/2014PPART
DetailsTony Young
Adam Phone #: ###-####,, rear basement/ retaining ftgs,, work in progress
BLD-Footing12/3/201412/3/201412/3/2014PNR
DetailsTony Young
Adam Phone #: ###-####,, need soils report
BLD-Foundation11/6/201411/6/201411/6/2014PPEND
DetailsPhil Shearer
Retaining wall rebar/requests 2 pm inspection, pouring at 3 - JR Phone #: ###-#### Retaining wall. Rebar ok as per engineered drawings that the contractor provided. There were not aproved drawing for this the retaining walls.
BLD-Foundation11/5/201411/5/201411/6/2014PPEND
DetailsPhil Shearer
JR-pour time 3:00 Phone #: ###-####. Retaining wall. Rebar ok as per engineered drawings that the contractor provided. There were not aproved drawing for this the retaining walls.
BLD-Footing11/3/201411/4/201411/4/2014PPEND
DetailsTony Young
JR-pour time 3:00 Phone #: ###-####retaining ftgs,, pending soils