BLD-Final | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2016 | 7/1/2016 | 7/1/2016 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 6/28/2016 | 6/29/2016 | 6/29/2016 | A | PEND |
Dave Hannah
|
|
|
John// please call before Phone #: ###-#### ok after zoning finals
|
BLD-Energy code compliance | 3/24/2016 | 3/24/2016 | 3/24/2016 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 3/23/2016 | 3/24/2016 | 3/24/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 3/11/2016 | 3/14/2016 | 3/15/2016 | P | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### ok to insulate but needs to resubmit plans showing stairs and bouns room above garage
|
BLD-Wall Bracing | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | PASS |
Dave Hannah
|
|
|
JOHN Phone #: ###-####
|
BLD-Foundation | 11/2/2015 | 11/2/2015 | 11/2/2015 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Wall Bracing | 10/30/2015 | 11/2/2015 | 11/2/2015 | A | CANC |
Dave Hannah
|
|
|
Haviro Phone #: ###-####
|
BLD-Footing | 10/22/2015 | 10/22/2015 | 10/22/2015 | P | PASS |
Dave Hannah
|
|
|
Alavro Phone #: ###-####
|
Extend Permit 90/180 days | | 9/25/2015 | 9/25/2015 | | DONE |
Jason Blais
|
|
|
Permit extended 180 days. This is first extension request for an issued permit.
|
BLD - Request for Extension | 9/22/2015 | 9/23/2015 | 9/23/2015 | A | DONE |
Mike Jordan
|
|
|
Will be submitting a plan mod soon - Teri Phone #: ###-####. Left message with terry noting to send buiilding official a letter for extension and to explain why it is needed and when the work will begin. Also left my phone number for call back and any other questions contractor may have.
|