BLD-Final | 9/22/2014 | 9/23/2014 | 9/23/2014 | A | PASS |
Dave Hannah
|
|
|
Located on the third floor of the building in the South East corner. The conference room is directly East of the reception desk. Phone #: ###-#### Inspection requested via web by Jeremy Barber
|
DOC - Permit Finaled | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 9/18/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed. No signature card available on site.
|
BLD-Final | 9/17/2014 | 9/18/2014 | 9/19/2014 | A | NR |
Dave Hannah
|
|
|
Space is on the third floor of the building in the South East corner. The conference room ceiling is complete. Phone #: ###-#### Inspection requested via web by Jeremy Barber
|
BLD-Ceiling Grid Inspection | 9/3/2014 | 9/5/2014 | 9/5/2014 | A | PASS |
Dave Hannah
|
|
|
The conference room is on the third floor of the building to the East of the elevator bank. Phone #: ###-#### Inspection requested via web by Jeremy Barber
|
BLD-Framing/Rough-in | 8/25/2014 | 8/25/2014 | 8/25/2014 | P | PASS |
Dave Hannah
|
|
|
The space is on the third floor of the building and will be on the East side of the elevator bank. The space is occupied so the receptionist may ask what you need to look at. The conference room remodel is directly East of the reception desk. Phone #: ###-#### Inspection requested via web by Jeremy Barber
|