BLD-Final | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/15/2015 | 4/20/2015 | 4/20/2015 | P | NR |
Mike Jordan
|
|
|
Ron Phone #: ###-####
|
FIRE-Final Inspection | 4/15/2015 | 4/20/2015 | 4/20/2015 | A | FAIL |
Troy Cobbley
|
|
|
Life safety ok to pass when the project related fire sprinkler and fire alarm permits are passed.
|
BLD-Framing/Rough-in | 3/31/2015 | 4/1/2015 | 4/1/2015 | P | CANC |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/31/2015 | 4/1/2015 | 4/1/2015 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 3/26/2015 | 3/30/2015 | 3/30/2015 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Exterior soffit ok.
|
BLD-Energy code compliance | 3/12/2015 | 3/13/2015 | 3/13/2015 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Energy code compliance | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2015 | 3/9/2015 | 3/10/2015 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior steel stud and wood framed walls for mezz. ok.
|
BLD-Framing/Rough-in | 3/6/2015 | 3/6/2015 | 3/6/2015 | P | NR |
Phil Shearer
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior steel stud walls at loading dock.
|
BLD-Framing/Rough-in | 2/24/2015 | 2/25/2015 | 2/25/2015 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior shear wall and decking diaphragm for interior mezz.
|
BLD-Framing/Rough-in | 2/19/2015 | 2/20/2015 | 2/20/2015 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. joist hangar connections to 2.x6 per red built installation details.
|
BLD-Foundation | 2/12/2015 | 2/12/2015 | 2/12/2015 | P | PASS |
Jim Storey
|
|
|
Rebar // Jim Phone #: ###-####
|
BLD-Footing | 2/10/2015 | 2/11/2015 | 2/11/2015 | A | PASS |
Mike Jordan
|
|
|
Jim-would like mid morning if poss Phone #: ###-####. column pad footings for mezz, footing for loading dock retaining walls.
|
BLD-Foundation | 1/30/2015 | 1/30/2015 | 1/30/2015 | P | PART |
Mike Jordan
|
|
|
Rebar // Jim Phone #: ###-####.. work in progress on reinforcement for loading dock walls. Ok pending special inspection.
|
BLD-Other | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | PART |
Mike Jordan
|
|
|
Welding // Jim Phone #: ###-####. Panel to panel and beam pockets. Reviewed special inspection reports to date. All welding also inspected by special inspection.
|
BLD-Footing | 12/16/2014 | 12/18/2014 | 12/18/2014 | A | PART |
Mike Jordan
|
|
|
phone call from Jim for the change//JIm Phone #: ###-####. Work in progress on remainder of exterior footings and loading dock footings. Pending special inspection.
|
BLD-Footing | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Mike Jordan
|
|
|
JIm// pour time is 1pm Phone #: ###-####. Exterior footing on ridline C between grids 1.5 to 6.
|
BLD-Footing | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | DEFR |
Mike Jordan
|
|
|
Concrete tilt walls rebar - Jim Phone #: ###-####. Pending special inspection.
|
BLD-Foundation | 11/12/2014 | 11/14/2014 | 11/14/2014 | A | CANC |
Mike Jordan
|
|
|
Jim-rebar Phone #: ###-####
|
BLD-Foundation | 11/12/2014 | 11/12/2014 | 11/12/2014 | P | PASS |
Mike Jordan
|
|
|
Jim-rebar Phone #: ###-####. Concrete tilt panels 1 to 18 and 22 to32.
|
BLD-Footing | 10/22/2014 | 10/24/2014 | 10/24/2014 | P | PASS |
Mike Jordan
|
|
|
Jim-as early pm as possible pour time 1:30 Phone #: ###-####. interio column pad footings ok.
|