BLD-Final | 4/1/2015 | 4/2/2015 | 4/2/2015 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
FIRE-Final Inspection | 4/1/2015 | 4/2/2015 | 4/2/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in the new two story addition. This includes the stand alone elevator recall.
|
BLD-Final | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### temp ok for new addition
|
BLD-Conference | 1/23/2015 | 1/26/2015 | 1/26/2015 | A | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
FIRE-Conference | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | DONE |
Troy Cobbley
|
|
|
Went over phasing of the project with Tom.
|
BLD-Framing/Rough-in | 1/7/2015 | 1/8/2015 | 1/8/2015 | A | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### conf on stairs
|
BLD-Framing/Rough-in | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Jim Storey
|
|
|
tom Phone #: ###-#### refu area ok to cover
|
BLD-Framing/Rough-in | 12/10/2014 | 12/11/2014 | 12/11/2014 | P | FAIL |
Jim Storey
|
|
|
Tom Phone #: ###-#### area of refuse hold on this end of building/ roof ceilling and duct proction required.
|
BLD-Energy code compliance | 12/10/2014 | 12/11/2014 | 12/11/2014 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 12/9/2014 | 12/10/2014 | 12/10/2014 | P | PART |
Dave Hannah
|
|
|
Tom Phone #: ###-#### ok to insulate. Needsto install lat bracing in trusses ,king studs two ply trusses , plumbing rough in , air seal ok.
|
BLD-Framing/Rough-in | 11/18/2014 | 11/19/2014 | 11/19/2014 | A | PART |
Jim Storey
|
|
|
tom Phone #: ###-#### ok to pre rock for mech and ele pannel
|
BLD-Other | 10/28/2014 | 10/28/2014 | 10/29/2014 | P | PART |
Jim Storey
|
|
|
Rebar - Tom Phone #: ###-#### ok pending si report
|
BLD-Footing | 10/22/2014 | 10/23/2014 | 10/23/2014 | P | PASS |
Jim Storey
|
|
|
tom - late pm Phone #: ###-####
|