BLD-Final | 5/20/2015 | 5/20/2015 | 5/20/2015 | P | PASS |
Jim Storey
|
|
|
Late as possible - Mike Phone #: ###-####
|
FIRE-Final Inspection | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | PASS |
Thomas Walsh
|
|
|
Fire Life-safety inspection for new medical office building. Fire alarm and fire sprinklers were finaled. All other FLS systems inspected OK. Bldg Dept. permit signed off.
|
BLD-Final | 5/14/2015 | 5/15/2015 | 5/15/2015 | P | PART |
Jim Storey
|
|
|
Mike Phone #: ###-#### temp ok pending others.
|
FIRE-Final Inspection | 5/14/2015 | 5/15/2015 | 5/15/2015 | P | PART |
Katie Marron
|
|
|
Completed inspection on exit hardware, fire extinguishers, emergency lighting, street address. Fire alarm for sprinkler monitoring was not ready, need to test flows/tampers and duct detector.
|
FIRE-Conference | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | DONE |
Katie Marron
|
|
|
Walk through with Mike. Discussed life safety items to include exit signs, door hardware, fire extinguishers. Also discussed need for sprinkler underground flush, rough-in and hydrostatic test inspections.
|
BLD-Ceiling Grid Inspection | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | PASS |
Jim Storey
|
|
|
East Half ONLY; Mike Phone #: ###-#### pending fire aproval.
|
BLD-Energy code compliance | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PASS |
Jim Storey
|
|
|
Insulation // Mike Phone #: ###-####
|
BLD-Energy code compliance | 3/2/2015 | 3/3/2015 | 3/3/2015 | A | PASS |
Jim Storey
|
|
|
Insulation Exterior // Mike Phone #: ###-#### eastside ok
|
FIRE-Conference | 2/24/2015 | 2/25/2015 | 2/26/2015 | A | DONE |
Forrest France
|
|
|
On site conference regarding knox box location, revised floorplan at the conference/meeting rooms north side.
|
BLD-Framing/Rough-in | 2/20/2015 | 2/24/2015 | 2/24/2015 | A | PART |
Jim Storey
|
|
|
Mike Phone #: ###-#### exterior holddowns ok/roof insulation ok/ wall framing ok wip pending trades.
|
FIRE-Conference | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | DONE |
Forrest France
|
|
|
Regarding exiting, folding partitions, knox box location, etc.
|
BLD-Framing/Rough-in | 2/5/2015 | 2/6/2015 | 2/6/2015 | A | PART |
Jim Storey
|
|
|
Mike Phone #: ###-#### exterior sheer wip ok
|
BLD-Concrete | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | PASS |
Phil Shearer
|
|
|
Rebar - First thing please - Mike Phone #: ###-####
|
BLD-Foundation | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Dave Hannah
|
|
|
Mike-stem wall-pour time 1:00 Phone #: ###-####
|
BLD-Foundation | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Phil Shearer
|
|
|
rebar//Mike Phone #: ###-####. Footing south east corner of building, stem wall south west corner of builing and interior column footings. OK pending MTI inspection report.
|
BLD-Foundation | 11/25/2014 | 11/26/2014 | 11/27/2014 | A | PASS |
Phil Shearer
|
|
|
rebar//mike Phone #: ###-#### 2nd half of footing and 1st half of the stem wall
|
BLD-Footing | 11/20/2014 | 11/21/2014 | 11/21/2014 | P | PASS |
Jim Storey
|
|
|
rebar, before one if possible// mike Phone #: ###-#### si on site half placment of ft ok
|