Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberBLD14-02471
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 2141 E PARKCENTER BLVD
Project NameBown Medical Clinic
Customer Number 
ePlanReviewYes
Description
(ST. ALPHONSUS)(BOWN MEDICAL CLINIC) Permit to construct a new 13,056 s.f. non ambulatory medical clinic office building with all interior and exterior improvements. Interior of building separated into two distinctive programs. One area for rehabilitation and the other for patient care and employee work area and accessory use for medical use. X-ray room and equipment to be installed per manufacture instillation instructions. . Work to include interior finish and exterior site work including parking, trash enclosure and all site improvements per approved plans. This building is fully fire sprinklered. **ajs

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/20/20155/20/20155/20/2015PPASS
DetailsJim Storey
Late as possible - Mike Phone #: ###-####
FIRE-Final Inspection5/19/20155/20/20155/20/2015APASS
DetailsThomas Walsh
Fire Life-safety inspection for new medical office building. Fire alarm and fire sprinklers were finaled. All other FLS systems inspected OK. Bldg Dept. permit signed off.
BLD-Final5/14/20155/15/20155/15/2015PPART
DetailsJim Storey
Mike Phone #: ###-#### temp ok pending others.
FIRE-Final Inspection5/14/20155/15/20155/15/2015PPART
DetailsKatie Marron
Completed inspection on exit hardware, fire extinguishers, emergency lighting, street address. Fire alarm for sprinkler monitoring was not ready, need to test flows/tampers and duct detector.
FIRE-Conference5/5/20155/6/20155/6/2015ADONE
DetailsKatie Marron
Walk through with Mike. Discussed life safety items to include exit signs, door hardware, fire extinguishers. Also discussed need for sprinkler underground flush, rough-in and hydrostatic test inspections.
BLD-Ceiling Grid Inspection5/5/20155/6/20155/6/2015APASS
DetailsJim Storey
East Half ONLY; Mike Phone #: ###-#### pending fire aproval.
BLD-Energy code compliance3/19/20153/20/20153/20/2015APASS
DetailsJim Storey
Insulation // Mike Phone #: ###-####
BLD-Energy code compliance3/2/20153/3/20153/3/2015APASS
DetailsJim Storey
Insulation Exterior // Mike Phone #: ###-#### eastside ok
FIRE-Conference2/24/20152/25/20152/26/2015ADONE
DetailsForrest France
On site conference regarding knox box location, revised floorplan at the conference/meeting rooms north side.
BLD-Framing/Rough-in2/20/20152/24/20152/24/2015APART
DetailsJim Storey
Mike Phone #: ###-#### exterior holddowns ok/roof insulation ok/ wall framing ok wip pending trades.
FIRE-Conference2/23/20152/24/20152/24/2015ADONE
DetailsForrest France
Regarding exiting, folding partitions, knox box location, etc.
BLD-Framing/Rough-in2/5/20152/6/20152/6/2015APART
DetailsJim Storey
Mike Phone #: ###-#### exterior sheer wip ok
BLD-Concrete12/18/201412/19/201412/19/2014APASS
DetailsPhil Shearer
Rebar - First thing please - Mike Phone #: ###-####
BLD-Foundation12/9/201412/10/201412/10/2014APASS
DetailsDave Hannah
Mike-stem wall-pour time 1:00 Phone #: ###-####
BLD-Foundation12/4/201412/5/201412/5/2014APASS
DetailsPhil Shearer
rebar//Mike Phone #: ###-####. Footing south east corner of building, stem wall south west corner of builing and interior column footings. OK pending MTI inspection report.
BLD-Foundation11/25/201411/26/201411/27/2014APASS
DetailsPhil Shearer
rebar//mike Phone #: ###-#### 2nd half of footing and 1st half of the stem wall
BLD-Footing11/20/201411/21/201411/21/2014PPASS
DetailsJim Storey
rebar, before one if possible// mike Phone #: ###-#### si on site half placment of ft ok