Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD14-02475
StatusFinaled
Name MCCARTER-MOORHOUSE LLC
Site Address 1508 S CLOVERDALE RD
Project NameBoise Tech Cafe
Customer Number 
ePlanReviewYes
Description
(BOISE TECH CAFE' - 2ND STORY) Fire sprinkler system used for story increase. To remodel the 2nd story of a new 3 story building for a 1,890 square foot restaurant and commercial kitchen. This permit is intended to establish a Certificate of Occupancy for the entire 3,902 square foot 2nd story which includes the restaurant, commercial kitchen, restrooms, and offices. The occupant load of the restaurant is limited to 58 based on the available ventilation. The restrooms were constructed under the shell permit (BLD14-00819) and are required to be accessible to the disabled. The floor between the 2nd and 3rd story, including the balconies and the supporting structure, will be upgraded to be of 1-hr fire-resistance-rated construction. The floor between the 1st and 2nd story will be structurally upgraded to have a live load capacity of 100 pounds per square foot. Other work is to include interior nonbearing walls, millwork, and kitchen equipment. The work is required to comply with the approved drawings, with the structural engineer’s calculations and design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/12/201412/15/201412/15/2014APASS
DetailsMike Jordan
Final Inspection Please

Thanks David Moorhouse ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. ok for perm occ.
FIRE-Final Inspection12/11/201412/12/201412/12/2014PPASS
DetailsTroy Cobbley
Fire life safety passed
BLD-Other10/28/201410/28/201410/28/2014APASS
DetailsMike Jordan
Please inspect 1st layer of ceiling sheetrock on 2nd floor. Please come as early as possible.

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Energy code compliance10/23/201410/23/201410/23/2014PPASS
DetailsDave Hannah
Please inspect Insulation

Thanks,
Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Framing/Rough-in10/20/201410/20/201410/20/2014PPASS
DetailsMike Jordan
Framing Inspection 2nd Floor location of Tech cafe

Thanks Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All framing issues on 3rd floor have been repaired, 2nd. floor framing ok to insulate. !st floor columns are now ok to cover.