BLD-Final | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, ok to move items in,, need to make hand rail meet code
|
BLD-Final | 5/28/2015 | 5/29/2015 | 5/29/2015 | A | PEND |
Tony Young
|
|
|
Eric Phone #: ###-####
|
BLD-Final | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, all ok except the upper exterior guard/hand rail
|
FIRE-Final Inspection | 5/27/2015 | 5/28/2015 | 5/28/2015 | P | CANC |
Troy Cobbley
|
|
|
No life safety sign off required. I left message on contacts voice mail
|
BLD-Framing/Rough-in | 3/5/2015 | 3/6/2015 | 3/6/2015 | P | PART |
Tony Young
|
|
|
change day per Eric Phone #: ###-####,, c/n posted on front stairs to meet code by final,, ok to cover interior
|
BLD-Energy code compliance | 3/5/2015 | 3/6/2015 | 3/6/2015 | A | PASS |
Tony Young
|
|
|
Eric Phone #: ###-####
|
BLD-Conference | 3/5/2015 | 3/5/2015 | 3/5/2015 | P | FAIL |
Tony Young
|
|
|
Stair consult - Eric Phone #: ###-####,, exterior stairs not per code at this point
|
BLD-Framing/Rough-in | 3/3/2015 | 3/4/2015 | 3/4/2015 | A | PASS |
Tony Young
|
|
|
Eric Phone #: ###-#### please call 1/2 hr prior,, ok to insulate
|
BLD-Framing/Rough-in | 3/2/2015 | 3/3/2015 | 3/3/2015 | A | PEND |
Tony Young
|
|
|
Eric Phone #: ###-#### please call 1/2 hr prior
|
BLD-Framing/Rough-in | 3/2/2015 | 3/2/2015 | 3/2/2015 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-#### please call 1/2 hr prior,, ok to start insulation,, verify elec pass,, redo some shear by front door,, nail girders off,,, strap plates,, add nails in hangers,, add hangers as needed
|
BLD-Wall Bracing | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | PART |
Tony Young
|
|
|
Shear // Eric Phone #: ###-####,, ok to build double wall on exterior,, need engineer to ok other shear as built or provide fixes due to changes with hold downs and openings
|
BLD-Foundation | 11/21/2014 | 11/21/2014 | 11/21/2014 | A | PART |
Jim Sly
|
|
|
Pat-WALL Phone #: ###-#### Walls at Stairway and 10' South retaining wall.
|
BLD-Foundation | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PEND |
Jim Sly
|
|
|
Pat Phone #: ###-#### Told Contractor they cannot pour per cold weather concrete provisions.
|
BLD-Footing | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PART |
Jim Sly
|
|
|
Pat Phone #: ###-#### 80 percent complete WIP appears OK.
|