Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberBLD14-02632
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 7609 W OVERLAND RD
Project NameBoise Spectrum
Customer Number 
ePlanReviewYes
Description
(Boise Spectrum) For upgrades to the facades for three existing buildings and the addition of a fire pit with work to include the demolition of some of the exterior facades and installation of new exterior finishes to include new EIFS, furred out vertical wood finishes on the type V buildings and decorative metal screaning on the type V multi use building and noncombustible metal screaning on the type II IMAX theater building. A new fire pit is being added between the buildings with bench seating around the perimeter. All work per the approved plans. These are fully fire sprinklered buildings with the exception of the fire pit structure; any alerations to the sprinkler system eill require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/22/20159/23/20159/23/2015PPASS
DetailsMike Jordan
Tom Phone #: ###-####
DOC - Permit Finaled9/23/20159/23/20159/23/2015PPASS
DetailsMike Jordan
DOC - Permit Finaled9/23/20159/23/20159/23/2015PPASS
DetailsMike Jordan
FIRE-Final Inspection9/22/20159/23/20159/23/2015APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection9/17/20159/18/20159/18/2015AFAIL
DetailsTroy Cobbley
Life safety will be ok to final when the two project related fire sprinkler permits are finaled
BLD-Final9/17/20159/18/20159/18/2015PCANC
DetailsMike Jordan
Tom Phone #: ###-####
BLD-Conference7/14/20157/15/20157/15/2015APEND
DetailsMike Jordan
Tom Phone #: ###-####. Wants to open courtyard area. Needs zoning, electrical, mech, and public works to ok this area prior to use. Noted that all construction within the courtyard area is completed.
FIRE-Conference7/7/20157/8/20157/8/2015ADONE
DetailsTroy Cobbley
Tom and I went over the location for the "Emergency Stop" sign for the gas valve to the outdoor fire pit. I'm ok for the fire pit area to be used.
BLD-Conference7/7/20157/8/20157/8/2015ACANC
DetailsMike Jordan
Tom Phone #: ###-####
FIRE-Conference6/25/20156/26/20156/29/2015ADONE
DetailsJim Page
Questioned regarding the location of a fire extinguisher for the outside fire pit, surveyed and verified an acceptable location.
BLD-Foundation5/5/20155/5/20155/5/2015PPASS
DetailsMike Jordan
Tom-rebar Phone #: ###-####. Column footings for new signs westside of building C.
BLD-Footing5/5/20155/5/20155/5/2015PCANC
DetailsMike Jordan
rebar Phone #: ###-####
BLD-Framing/Rough-in4/29/20154/30/20154/30/2015APASS
DetailsMike Jordan
Tom Phone #: ###-####. Steel stud framing for new headers where existing arches where removed.
BLD-Footing4/30/20154/30/20154/30/2015APASS
DetailsMike Jordan
Tom Phone #: ###-####. Footing for new columns for new signs, east side of building B.