BLD-Final | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | PASS |
Dave Hannah
|
|
|
Final inspection, glass sidelights complete. Ready for PM inspection, call Adam prior, ###-####. thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Final | 12/19/2014 | 12/23/2014 | 12/24/2014 | P | PART |
Dave Hannah
|
|
|
Building final inspection request/walk with Dave H. Call Adam prior to inspection visit. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson ok for temp occ needs to install glass.
|
FIRE-Final Inspection | 12/19/2014 | 12/23/2014 | 12/23/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory including trade related permit work. Project related fire sprinkler permit okayed for final- scheduled for 12/24 AM.
|
BLD-Ceiling Grid Inspection | 12/16/2014 | 12/17/2014 | 12/17/2014 | A | PASS |
Dave Hannah
|
|
|
Ceiling Grid reinspection, call Adam prior to inspection, ###-####. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/15/2014 | 12/16/2014 | 12/16/2014 | P | CANC |
Dave Hannah
|
|
|
Ceiling Grid reinspection, call Adam prior to inspection, ###-####. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson Inspection cancelled from web by: Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/10/2014 | 12/11/2014 | 12/11/2014 | A | NR |
Dave Hannah
|
|
|
Ceiling grid inspection request, Stifel TI, 12th Floor at 8th and Main. Please call Adam prior to inspection. Thanks AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Jim Storey
|
|
|
Framing inspection request, Stifel TI, 12th Floor, call Adam prior to inspection ###-####. thanks akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|