BLD-Final | 12/29/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Jim Sly
|
|
|
Cody Phone #: ###-####
|
FIRE-Final Inspection | 12/29/2016 | 12/30/2016 | 12/30/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 12/23/2016 | 12/23/2016 | 12/23/2016 | P | PART |
Troy Cobbley
|
|
|
Life safety passed in apartments 107, 108, 207, 208, 307 and 308. Waiting on the corrected as-builts for the fire sprinkler system prior to a final sign off.
|
FIRE-Final Inspection | 12/19/2016 | 12/19/2016 | 12/19/2016 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 105, 106, 205, 206, 305 and 306
|
BLD-Final | 12/13/2016 | 12/13/2016 | 12/13/2016 | P | PART |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Ok for
Temp C of O for units 103,104,203,204,303,304 only.
|
FIRE-Final Inspection | 12/9/2016 | 12/12/2016 | 12/12/2016 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 103, 104, 203, 204, 303, 304
|
FIRE-Final Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled.
|
BLD-Final | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PART |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Ok to occupy units 101,102,201,202,301,302 only.
|
FIRE-Final Inspection | 11/23/2016 | 11/29/2016 | 11/29/2016 | A | PART |
Troy Cobbley
|
|
|
Life safety passed only for apartments 101, 102, 201, 202, 301, 302.
|
FIRE-Final Inspection | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire sprinkler and and fire alarm permits addressed prior to an inspection.
|
BLD-Wall cover | 10/18/2016 | 10/18/2016 | 10/18/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Hat channel, 1st and 2nd. floors, north units ok.
|
BLD-Wall Bracing | 10/14/2016 | 10/17/2016 | 10/17/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Hat channel ok.
|
BLD-Wall cover | 10/13/2016 | 10/14/2016 | 10/14/2016 | A | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. 2nd. floor, hat channel, central corridor, north units.
|
BLD-Framing/Rough-in | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Hat channel, 1st floor center units, north side.
|
BLD-Energy code compliance | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Mike Jordan
|
|
|
1st, 2nd. floors north units ok.
|
BLD-Energy code compliance | 10/7/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. 1st,2nd and 3rd floors, central corridor, north half. 3rd. floor north end units ok.
|
BLD-Framing/Rough-in | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | PASS |
Mike Jordan
|
|
|
cody Phone #: ###-####. All framing issues resolved on 1st., 2nd., and 3rd. floors north half of building. Ok to insulate.
|
BLD-Wall cover | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. 1st. floor hat channel ok.
|
BLD-Framing/Rough-in | 10/4/2016 | 10/4/2016 | 10/4/2016 | P | FAIL |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Complete all firestopping, fireblocking. Block and nail off all interior shear walls. Provide UL listed washer box. Provide 2 layers 5/8 type x rock on 1hr. horizontal floor ceiling assembly aboce furnace in ADA apartment.
|
BLD-Wall cover | 10/3/2016 | 10/4/2016 | 10/4/2016 | A | PASS |
Mike Jordan
|
|
|
Cody// 2nd floor Phone #: ###-####
|
BLD-Wall cover | 9/26/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Mike Jordan
|
|
|
Dry wall // Cody Phone #: ###-####. Unites 107,108,207 and 208.
|
BLD-Energy code compliance | 9/23/2016 | 9/23/2016 | 9/23/2016 | P | PASS |
Dave Hannah
|
|
|
Cody Phone #: ###-#### units 103 104 203 204 303 and 304 ok to cover
|
BLD-Energy code compliance | 9/22/2016 | 9/22/2016 | 9/22/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. 1st, 2nd, 3rd. floor sother most six units.
|
BLD-Framing/Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 | A | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Ok to isulate 1st, 2nd. and 3rd floors, south half only.
|
BLD-Framing/Rough-in | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | FAIL |
Mike Jordan
|
|
|
Cody Phone #: ###-####
|
BLD-Framing/Rough-in | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | FAIL |
Mike Jordan
|
|
|
Cody Phone #: ###-####. See corrections list.
|
BLD-Wall Bracing | 8/26/2016 | 8/29/2016 | 8/29/2016 | A | PASS |
Mike Jordan
|
|
|
Shear // Cody Phone #: ###-####
|
BLD-Wall cover | 8/26/2016 | 8/26/2016 | 8/26/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####, SOuth units, 2nd floor fur downs.
|
BLD-Wall Bracing | 8/25/2016 | 8/25/2016 | 8/26/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Ok to rock corridors.
|
BLD-Other | 8/23/2016 | 8/24/2016 | 8/24/2016 | P | PASS |
Mike Jordan
|
|
|
RC1 channel; Tony Phone #: ###-####
|
BLD-Other | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | CANC |
Mike Jordan
|
|
|
Cody-wall bracing Phone #: ###-####
|
BLD-Wall Bracing | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | FAIL |
Mike Jordan
|
|
|
Cody-wall bracing Phone #: ###-####. Missing floor to floor straps and hold downs. Also missing several areas on exterior and interior shear.
|
BLD-Wall cover | 5/17/2016 | 5/18/2016 | 5/18/2016 | A | PASS |
Mike Jordan
|
|
|
Shear // Pat Phone #: ###-####. south half crawl space.
|
BLD-Wall Bracing | 5/3/2016 | 5/4/2016 | 5/4/2016 | A | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. 2nd. floor exterior shear, north building.
|
BLD-Foundation | 4/27/2016 | 4/27/2016 | 4/27/2016 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Wall bracing and holdowns in crawl space.
|
BLD-Foundation | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | NR |
Mike Jordan
|
|
|
Manul Phone #: ###-####. Contractor not ready.
|
BLD-Footing | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|