Permit Information
Permit NumberBLD14-03071
StatusFinaled
Name BILTMORE COMPANY
Site Address 6017 W OPOHONGA ST
Project NamePalisades Apartments
Customer NumberBLD14-03070
ePlanReviewNo
Description
Palisades Apartments - Building B - To construct a new 23,000 square foot, three story, wood framed, 24 unit multi-family apartment building and related site improvements. This building will have an NFPA 13R sprinkler system. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/29/20169/30/20169/30/2016APART
DetailsMike Jordan
Cody Phone #: ###-####. units 105,106,205,206,305,306 are ok to occupy. Will be ok for perm occ. once all other associated trade permits sign perm.
BLD-Final9/28/20169/29/20169/29/2016APASS
DetailsMike Jordan
Cody// inspection for the 3rd Phone #: ###-####. units 107,108,207,208,307,308 ok to occupy only.
FIRE-Final Inspection9/28/20169/29/20169/29/2016APASS
DetailsTroy Cobbley
Life safety passed. Today I inspected units 105, 106, 205, 206, 305, 306
BLD-Final9/12/20169/13/20169/13/2016AFAIL
DetailsMike Jordan
Cody Phone #: ###-####. Complete all firestopping, doors to be self closing, provide listed approved membrane opening protection for water shut off in 1hr. fire partition.
FIRE-Final Inspection9/8/20169/9/20169/9/2016APART
DetailsTroy Cobbley
Life safety passed for units 107,108,207,208,307,308
BLD-Final9/7/20169/7/20169/7/2016PPASS
DetailsMike Jordan
Cody Phone #: ###-####. OK to occupy rooms304 and 303 only.
BLD-Final9/1/20169/1/20169/1/2016PPASS
DetailsMike Jordan
Cody Phone #: ###-####. Ok to occupy 103, 104, 203 and 204 only.
FIRE-Final Inspection8/31/20169/1/20169/1/2016APART
DetailsTroy Cobbley
Life safety passed in apartments 103,104,203,204,303,304.
BLD-Final8/11/20168/12/20168/12/2016APART
DetailsMike Jordan
Cody Phone #: ###-####. Temp occ. Ok to occupy units 101,102.201,202,301,302 only. These are the six units on the north end accessed by the the north stairs only.
BLD-Final8/10/20168/11/20168/11/2016PFAIL
DetailsMike Jordan
Cody Phone #: ###-####. Firestop all plumbing penetrations where required.
BLD-Final8/5/20168/5/20168/5/2016PNR
DetailsMike Jordan
Cody Phone #: ###-####. Needs zoning and public works.
FIRE-Final Inspection8/1/20168/2/20168/2/2016APART
DetailsTroy Cobbley
Life safety passed for apartments 101,102, 201,202, 301, 302. (North end). Fire sprinkler and fire alarm systems are fully functional.
BLD-Wall cover7/22/20167/25/20167/25/2016APASS
DetailsJim Sly
RC1 // Cody Phone #: ###-####
BLD-Other7/11/20167/11/20167/11/2016PPASS
DetailsPhil Shearer
RC1 Channel; Pat Phone #: ###-####
BLD-Energy code compliance7/7/20167/8/20167/8/2016APASS
DetailsMike Jordan
Cody Phone #: ###-####
BLD-Energy code compliance7/6/20167/6/20167/6/2016PPASS
DetailsMike Jordan
Cody Phone #: ###-####. 1st-3rd. floors, south end units only. south central portion work in progress.
BLD-Framing/Rough-in6/30/20167/1/20167/1/2016APASS
DetailsMike Jordan
Cody Phone #: ###-####. All issues resolved. 1stg and 2nd floor south half ok to insulate. #rd floor pend. fire sprinkler rough in prior to insulation.
BLD-Framing/Rough-in6/29/20166/30/20166/30/2016AFAIL
DetailsMike Jordan
Cody Phone #: ###-####. Complete all fire caulking and fire blocking. Block floor to flor straps, remove non rated boxes from reated walls.
BLD-Other6/23/20166/24/20166/24/2016APASS
DetailsMike Jordan
sheetrock; Cody Phone #: ###-####. 1st and 2nd floor base layer of 5/8 type x and hat channel for floor ceiling assembly.
BLD-Other6/15/20166/16/20166/16/2016APASS
DetailsMike Jordan
RC1 Channel unit 102 201 202 // Pat Phone #: ###-####
BLD-Energy code compliance6/14/20166/14/20166/14/2016PPASS
DetailsMike Jordan
Pat Phone #: ###-####. 1st and 2nd floors, north half of building ok to sheet rock.
BLD-Energy code compliance6/13/20166/13/20166/13/2016PPART
DetailsMike Jordan
Pat Phone #: ###-####. Needs to provide additional barrier to back side of insulation on 3rd floor caufeered ceilings.
BLD-Framing/Rough-in6/6/20166/6/20166/6/2016PPART
DetailsMike Jordan
Pat Phone #: ###-####. Framing inspection 1st. to third floors north half only. Neeeds to complete all fireblocking, interior straping, provide listing for washer boxes and door frames in corridor and complete LSL blocking on 2nd floor and continue OSB sheathing on interior shear walls to roof deck and brace them per plans. ok to insulate these areas only.
BLD-Framing/Rough-in6/3/20166/3/20166/3/2016PPART
DetailsJim Sly
Pat Phone #: ###-####
Inspection of floor to floor straps on exterior of N. E. and S. walls OK excluding straps to be installed on interior side because of exterior decks installed before straps. Interior location may require approval.
BLD-Framing/Rough-in5/31/20165/31/20165/31/2016PPASS
DetailsMike Jordan
Pat Phone #: ###-####. Ok to cover west exterior of uilding only.
BLD-Framing/Rough-in5/20/20165/23/20165/23/2016AFAIL
DetailsMike Jordan
Pat Phone #: ###-####. Install missing h2.5, provide fix for m77 and m37 trusses that require contionous bearing.
BLD-Framing/Rough-in5/19/20165/20/20165/20/2016PCANC
DetailsMike Jordan
Moved to monday morning. Framer could not make it to job site.
BLD-Framing/Rough-in5/19/20165/19/20165/20/2016PFAIL
DetailsMike Jordan
Work in progress on 1st, 2nd and 3rd. floors. Needs to fireblock fur downs, Provide the hat channel and additional layer of 5/8 type x rock to complete the floor ceiling assembly above fur downs. Provide 5/8 type x rock behind tub/shower stalls. Needs to box out washer boxes as well.
BLD-Wall Bracing5/19/20165/19/20165/20/2016PFAIL
DetailsMike Jordan
Needs to install all exterior and interior floor to floor straps, complete the sheating from interior shear walls on 3rd floor to underneath side of roof deck and provide the kicker supprts as per the approved plans. Also noted ares on interior shear walls not yet attached.
BLD-Wall Bracing5/19/20165/20/20165/20/2016ACANC
DetailsMike Jordan
moved to pm.
BLD-Framing/Rough-in5/18/20165/19/20165/19/2016ACANC
DetailsMike Jordan
Pat Phone #: ###-####-please call prior to meet. Moved to pm.
BLD-Wall Bracing3/25/20163/25/20163/25/2016PPASS
DetailsMike Jordan
Pat Phone #: ###-####. 2nd. floor exterior wall bracing only ok.
BLD-Conference3/23/20163/23/20163/23/2016ADONE
DetailsMike Jordan
Stop by job site to see job to check job progress. 1st floor has been framed, and working on sheeting the 2nd. floor decking.
BLD-Wall Bracing3/4/20163/7/20163/7/2016ACANC
DetailsMike Jordan
BLD-Wall Bracing3/4/20163/4/20163/4/2016PNR
DetailsMike Jordan
BLD-Wall Bracing3/3/20163/4/20163/4/2016ANR
DetailsMike Jordan
BLD-Wall cover3/3/20163/3/20163/3/2016PNR
DetailsMike Jordan
Shear // Pat Phone #: ###-####
BLD-Wall Bracing3/1/20163/1/20163/1/2016PPASS
DetailsMike Jordan
Pat Phone #: ###-####. Holdowns and shearwalls in crawl space.
BLD-Foundation2/16/20162/16/20162/16/2016PPASS
DetailsMike Jordan
wall // Manuel Phone #: ###-####. Stemwall and interior footings ok. Contractor to get RFI from engineer of record indicating the deletion of plate washers and continous erbar from exterior to interior footing transitions.
BLD-Footing2/11/20162/11/20162/11/2016PPASS
DetailsMike Jordan
Manuel Phone #: ###-####. Permiter footings only.