BLD-Final | 9/29/2016 | 9/30/2016 | 9/30/2016 | A | PART |
Mike Jordan
|
|
|
Cody Phone #: ###-####. units 105,106,205,206,305,306 are ok to occupy. Will be ok for perm occ. once all other associated trade permits sign perm.
|
BLD-Final | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Mike Jordan
|
|
|
Cody// inspection for the 3rd Phone #: ###-####. units 107,108,207,208,307,308 ok to occupy only.
|
FIRE-Final Inspection | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Today I inspected units 105, 106, 205, 206, 305, 306
|
BLD-Final | 9/12/2016 | 9/13/2016 | 9/13/2016 | A | FAIL |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Complete all firestopping, doors to be self closing, provide listed approved membrane opening protection for water shut off in 1hr. fire partition.
|
FIRE-Final Inspection | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for units 107,108,207,208,307,308
|
BLD-Final | 9/7/2016 | 9/7/2016 | 9/7/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. OK to occupy rooms304 and 303 only.
|
BLD-Final | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Ok to occupy 103, 104, 203 and 204 only.
|
FIRE-Final Inspection | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in apartments 103,104,203,204,303,304.
|
BLD-Final | 8/11/2016 | 8/12/2016 | 8/12/2016 | A | PART |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Temp occ. Ok to occupy units 101,102.201,202,301,302 only. These are the six units on the north end accessed by the the north stairs only.
|
BLD-Final | 8/10/2016 | 8/11/2016 | 8/11/2016 | P | FAIL |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Firestop all plumbing penetrations where required.
|
BLD-Final | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | NR |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Needs zoning and public works.
|
FIRE-Final Inspection | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 101,102, 201,202, 301, 302. (North end). Fire sprinkler and fire alarm systems are fully functional.
|
BLD-Wall cover | 7/22/2016 | 7/25/2016 | 7/25/2016 | A | PASS |
Jim Sly
|
|
|
RC1 // Cody Phone #: ###-####
|
BLD-Other | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | PASS |
Phil Shearer
|
|
|
RC1 Channel; Pat Phone #: ###-####
|
BLD-Energy code compliance | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####
|
BLD-Energy code compliance | 7/6/2016 | 7/6/2016 | 7/6/2016 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. 1st-3rd. floors, south end units only. south central portion work in progress.
|
BLD-Framing/Rough-in | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. All issues resolved. 1stg and 2nd floor south half ok to insulate. #rd floor pend. fire sprinkler rough in prior to insulation.
|
BLD-Framing/Rough-in | 6/29/2016 | 6/30/2016 | 6/30/2016 | A | FAIL |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Complete all fire caulking and fire blocking. Block floor to flor straps, remove non rated boxes from reated walls.
|
BLD-Other | 6/23/2016 | 6/24/2016 | 6/24/2016 | A | PASS |
Mike Jordan
|
|
|
sheetrock; Cody Phone #: ###-####. 1st and 2nd floor base layer of 5/8 type x and hat channel for floor ceiling assembly.
|
BLD-Other | 6/15/2016 | 6/16/2016 | 6/16/2016 | A | PASS |
Mike Jordan
|
|
|
RC1 Channel unit 102 201 202 // Pat Phone #: ###-####
|
BLD-Energy code compliance | 6/14/2016 | 6/14/2016 | 6/14/2016 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. 1st and 2nd floors, north half of building ok to sheet rock.
|
BLD-Energy code compliance | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Needs to provide additional barrier to back side of insulation on 3rd floor caufeered ceilings.
|
BLD-Framing/Rough-in | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Framing inspection 1st. to third floors north half only. Neeeds to complete all fireblocking, interior straping, provide listing for washer boxes and door frames in corridor and complete LSL blocking on 2nd floor and continue OSB sheathing on interior shear walls to roof deck and brace them per plans. ok to insulate these areas only.
|
BLD-Framing/Rough-in | 6/3/2016 | 6/3/2016 | 6/3/2016 | P | PART |
Jim Sly
|
|
|
Pat Phone #: ###-#### Inspection of floor to floor straps on exterior of N. E. and S. walls OK excluding straps to be installed on interior side because of exterior decks installed before straps. Interior location may require approval.
|
BLD-Framing/Rough-in | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Ok to cover west exterior of uilding only.
|
BLD-Framing/Rough-in | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | FAIL |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Install missing h2.5, provide fix for m77 and m37 trusses that require contionous bearing.
|
BLD-Framing/Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | CANC |
Mike Jordan
|
|
|
Moved to monday morning. Framer could not make it to job site.
|
BLD-Framing/Rough-in | 5/19/2016 | 5/19/2016 | 5/20/2016 | P | FAIL |
Mike Jordan
|
|
|
Work in progress on 1st, 2nd and 3rd. floors. Needs to fireblock fur downs, Provide the hat channel and additional layer of 5/8 type x rock to complete the floor ceiling assembly above fur downs. Provide 5/8 type x rock behind tub/shower stalls. Needs to box out washer boxes as well.
|
BLD-Wall Bracing | 5/19/2016 | 5/19/2016 | 5/20/2016 | P | FAIL |
Mike Jordan
|
|
|
Needs to install all exterior and interior floor to floor straps, complete the sheating from interior shear walls on 3rd floor to underneath side of roof deck and provide the kicker supprts as per the approved plans. Also noted ares on interior shear walls not yet attached.
|
BLD-Wall Bracing | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | CANC |
Mike Jordan
|
|
|
moved to pm.
|
BLD-Framing/Rough-in | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####-please call prior to meet. Moved to pm.
|
BLD-Wall Bracing | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. 2nd. floor exterior wall bracing only ok.
|
BLD-Conference | 3/23/2016 | 3/23/2016 | 3/23/2016 | A | DONE |
Mike Jordan
|
|
|
Stop by job site to see job to check job progress. 1st floor has been framed, and working on sheeting the 2nd. floor decking.
|
BLD-Wall Bracing | 3/4/2016 | 3/7/2016 | 3/7/2016 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 3/4/2016 | 3/4/2016 | 3/4/2016 | P | NR |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 3/3/2016 | 3/4/2016 | 3/4/2016 | A | NR |
Mike Jordan
|
|
|
|
BLD-Wall cover | 3/3/2016 | 3/3/2016 | 3/3/2016 | P | NR |
Mike Jordan
|
|
|
Shear // Pat Phone #: ###-####
|
BLD-Wall Bracing | 3/1/2016 | 3/1/2016 | 3/1/2016 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Holdowns and shearwalls in crawl space.
|
BLD-Foundation | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PASS |
Mike Jordan
|
|
|
wall // Manuel Phone #: ###-####. Stemwall and interior footings ok. Contractor to get RFI from engineer of record indicating the deletion of plate washers and continous erbar from exterior to interior footing transitions.
|
BLD-Footing | 2/11/2016 | 2/11/2016 | 2/11/2016 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####. Permiter footings only.
|