Permit Information
Permit NumberBLD14-03175
StatusFinaled
Name BAKER CONSTRUCTION
Site Address 1001 W IDAHO ST
Project NameWashington Federal
Customer Number 
ePlanReviewYes
Description
(WASHINGTON FEDERAL - BASEMENT, 1ST STORY, 2ND STORY, 3RD STORY, 4TH STORY, AND PENTHOUSE) (2-5-16 PLAN MODIFICATION TO INSTALL COMPUTER EQUIPMENT WITHIN A COMPUTER ROOM LOCATED IN THE BASEMENT. TWO AIR HANDLERS LOCATED WITHIN THE COMPUTER ROOM AND TWO EXTERIOR CHILLERS WILL BE INSTALLED IN CONJUNCTION WITH THIS PLAN MODIFICATION. A SECTION OF WALL WILL BE REMOVED TO CONNECT TWO ROOMS CREATING ONE 597 SQUARE FOOT COMPUTER ROOM. IN ADDITION, A NEW FIRE PUMP AND FIRE PUMP CONTROLLER WILL BE INSTALLED IN A SEPARATE ROOM.) (9-21-15 PLAN MODIFICATION TO RECONFIGURE THE LAYOUT OF THE 3RD STORY.) (6-15-15 PLAN MODIFICATION TO CONSTRUCT A 441 SQUARE FOOT ENCLOSURE HAVING MASONRY WALLS (12 FEET TALL AND 10 INCHES THICK) AND NO ROOF TO SCREEN A NEW DIESEL BACK-UP GENERATOR. THE ENCLOSURE WILL BE LOCATED IN THE SOUTHEAST CORNER OF THE PARCEL. WORK IS TO INCLUDE CONTINUOUS CONCRETE FOOTINGS (3’-9” WIDE BY 2’-0” THICK) AND A CONCRETE SLAB ON GRADE (6” THICK). THE EXTERIOR WALL FINISH WILL BE BRICK VENEER AND STUCCO. THE WALLS ARE DESIGNED BEING FIXED AT THE BOTTOM AND FREE AT THE TOP WITHOUT A DIAPHRAGM AT THE TOP. SPECIAL INSPECTION IS REQUIRED FOR MASONRY AND POST INSTALLED CONCRETE ANCHORS.) To remodel the basement, 1st story, 2nd story, 3rd story, 4th story, and penthouse of an existing office building. Work includes the complete replacement of mechanical systems (except the existing chiller and the existing boilers) and upgrading the existing electrical service and system. Basement work is to include a new air handler unit, an enlarged exhaust air pit at grade, compacted gravel fill and a concrete slab at an existing mechanical pit, steel headers and jambs at widened openings in existing masonry walls, a steel header and steel jambs at a widened opening in an existing concrete wall, a masonry wall infill, concrete floor slabs at plumbing and electrical trenches, interior nonbearing walls, 2 restrooms accessible to the disabled, a 1-hr stairway enclosure extension and poured in place concrete steps, 1-hr mechanical shaft extensions and repairs, new interior doors, new interior windows, suspended acoustical ceilings, millwork, and finishes. Cooking operations within the Pantry that create grease laden vapors or that expose the sewer system to grease are NOT allowed. 1st story work is limited to replacing exterior doors and sidelights. 2nd story work includes interior nonbearing walls, 2 restrooms accessible to the disabled, new drinking fountains, suspended acoustical ceilings, millwork, and finishes. 3rd story work includes a 1-hr shaft extension adjacent to an existing stairway enclosure, the structural support for a new floor system between the 2nd and 3rd stories, and suspended acoustical ceilings. 4th story work includes interior nonbearing walls, 2 restrooms accessible to the disabled, suspended acoustical ceilings, millwork, and finishes. Penthouse work includes a new air handler unit, a new opening in the penthouse floor for a new return air duct, and a concrete floor patch where the old return air duct was located. Special Inspection is required for concrete, bolting, welding, epoxy anchors, and expansion anchors. The work is required to comply with the approved drawings, with the plan review report, with the structural design, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13, including quick-response fire sprinkler heads installed throughout the building where required, and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/21/20164/22/20164/22/2016APASS
DetailsDave Hannah
John Phone #: ###-####
FIRE-Final Inspection4/21/20164/21/20164/21/2016PPASS
DetailsJim Page
Final fire sprinkler inspections complete, final fire pump relocation inspections complete, final fire alarm inspections complete. Fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIRE-Final Inspection4/20/20164/20/20164/20/2016PCANC
DetailsJim Page
Inspection request cancelled, cannot complete life fire safety inspection with FIR permit for alarms still in issued status. Fire alarm permit needs to be inspected/finaled before life fire safety inspection can be completed and finaled.
BLD-Aging Inspection4/4/20164/4/20164/4/2016 PEND
DetailsDave Hannah
BLD-Aging Inspection2/3/20162/3/20162/4/2016 PEND
DetailsDave Hannah
BLD-Final11/20/201511/24/201511/25/2015PPART
DetailsDave Hannah
John Phone #: ###-#### 4th floor ok to occ 4th floor
FIRE-Final Inspection11/20/201511/24/201511/24/2015APART
DetailsJim Page
Fire sprinkler inspection complete for 4th floor, fire alarm inspections complete for 4th floor. Life fire safety inspection passed/complete for 4th floor.
FIRE-Final Inspection11/4/201511/5/201511/5/2015APART
DetailsJim Page
Life fire safety passed/complete for 1st floor.
BLD-Final11/4/201511/5/201511/5/2015APART
DetailsMike Jordan
John// for the 1st floor Phone #: ###-####. Ok to occupy 1st. floor.
BLD-Ceiling Grid Inspection10/21/201510/22/201510/22/2015PPASS
DetailsDave Hannah
4th floor // John Phone #: ###-####
BLD-Final10/14/201510/15/201510/15/2015PPART
DetailsDave Hannah
John-3rd floor Phone #: ###-#### ok to occ third floor
FIRE-Final Inspection10/14/201510/15/201510/15/2015APART
DetailsJim Page
Third floor final life fire safety inspection passed/complete
BLD-Ceiling Grid Inspection9/30/201510/1/201510/2/2015PPASS
DetailsDave Hannah
3rd floor // John Phone #: ###-####
BLD-Framing/Rough-in9/21/20159/22/20159/22/2015APASS
DetailsMike Jordan
4th floor hardlids for restroom and soffits.
BLD-Framing/Rough-in9/21/20159/21/20159/21/2015PDEFR
DetailsPhil Shearer
John--- inspection for 4th floor Phone #: ###-####. Out of time
BLD-Framing/Rough-in9/11/20159/14/20159/14/2015APART
DetailsJim Sly
4th floor; John Phone #: 509-475-
Everything on 4th floor except........Boardroom Elevator lobby Bathrooms.
BLD-Framing/Rough-in9/1/20159/1/20159/1/2015PPASS
DetailsDave Hannah
3rd floor; John Phone #: ###-####
BLD-Final6/30/20157/1/20157/2/2015PPART
DetailsDave Hannah
John Phone #: ###-#### ok to occ second floor and north half of basement
FIRE-Final Inspection6/30/20157/1/20157/1/2015APART
DetailsJim Page
Superintendent called in for final on basement level as well as second floor, second floor passed life fire safety, basement level still has sprinkler work in mechanical room to be completeed at later date, basement level with exception to mech room finaled.
FIRE-Final Inspection6/29/20156/30/20156/30/2015PCANC
DetailsJim Page
Inspection canceled per conversation with John Phone #: ###-####, superintendent of job, items on job need to be corrected/repaired before inspection can be performed.
BLD-Ceiling Grid Inspection6/19/20156/19/20156/19/2015PPASS
DetailsMike Jordan
2nd floor, would like late; John Phone #: ###-####
BLD-Ceiling Grid Inspection6/12/20156/15/20156/15/2015PPART
DetailsDave Hannah
John Phone #: ###-#### basement ok to cover
BLD-Ceiling Grid Inspection5/27/20155/28/20155/28/2015APASS
DetailsMike Jordan
John Phone #: ###-####. grid in training rm only.
BLD-Framing/Rough-in5/18/20155/18/20155/18/2015PPASS
DetailsDave Hannah
2nd floor // John Phone #: ###-####
BLD-Framing/Rough-in5/14/20155/15/20155/15/2015PNR
DetailsJim Storey
John-2nd floor Phone #: ###-####
BLD-Framing/Rough-in5/4/20155/5/20155/6/2015PDONE
DetailsDave Hannah
John Phone #: ###-####
BLD-Framing/Rough-in5/6/20155/6/20155/6/2015APASS
DetailsDave Hannah
John Phone #: ###-####
BLD-Framing/Rough-in4/21/20154/22/20154/23/2015PPART
DetailsDave Hannah
John Phone #: ###-#### walls in basement area around meeting rooms
BLD-Conference4/7/20154/8/20154/8/2015PPEND
DetailsDave Hannah
John-would like a 2:00 meet time Phone #: ###-####