BLD-Final | 1/5/2015 | 1/6/2015 | 1/6/2015 | P | PASS |
Dave Hannah
|
|
|
Please call ahead - Matt Phone #: ###-####
|
FIRE-Final Inspection | 1/5/2015 | 1/6/2015 | 1/6/2015 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Final Inspection | 1/5/2015 | 1/5/2015 | 1/5/2015 | P | PASS |
Forrest France
|
|
|
Noted corrections completed. Fire life safety finaled.
|
BLD-Final | 12/30/2014 | 1/2/2015 | 1/5/2015 | A | NR |
Dave Hannah
|
|
|
Brad-please call before you head out Phone #: ###-####
|
FIRE-Final Inspection | 12/30/2014 | 12/31/2014 | 12/31/2014 | P | NR |
Forrest France
|
|
|
Need project related fire sprinkler permit work completed and scheduled for inspection prior to fire life safety final.
|
FIRE-Conference | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | DONE |
Forrest France
|
|
|
Regarding fire sprinkler coverage at the tenant remodel area.
|
BLD-Final | 12/23/2014 | 12/24/2014 | 12/24/2014 | P | NR |
Dave Hannah
|
|
|
Brad Phone #: ###-#### needs fire finals
|
FIRE-Final Inspection | 12/24/2014 | 12/24/2014 | 12/24/2014 | P | FAIL |
Forrest France
|
|
|
Modifications to the existing fire sprinkler system will be necessary due to remodel work- noted spacing and coverage issues, missing PFE per plan, revise room use on the drawings to match field conditions (office and video conference rooms are reversed).
|
BLD-Framing/Rough-in | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|