BLD-Final | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PASS |
Jim Sly
|
|
|
Richard Phone #: ###-#### OK for Perm Occ
|
FIRE-Final Inspection | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Sprinkler Rough-in | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | DONE |
Troy Cobbley
|
|
|
Inspection was actually for a conference about the fire hydrant. The new fire hydrant has been installed too close to the side walk so that when the fence is installed the 3'-0" clearance can not be met. Also the 5" barrel is installed the wrong direction when the fence is installed. I ended up deferring Jake to Romeo for any variance.
|
BLD-Framing/Rough-in | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | PASS |
Jim Storey
|
|
|
Richard Phone #: ###-####
|
BLD-Foundation | 5/5/2015 | 5/5/2015 | 5/5/2015 | P | PASS |
Jim Sly
|
|
|
Richard-slab Phone #: ###-####
|
BLD-Foundation | 5/4/2015 | 5/4/2015 | 5/4/2015 | P | PASS |
Jim Sly
|
|
|
RICHARD Phone #: ###-####
|
BLD-Foundation | 4/23/2015 | 4/23/2015 | 4/24/2015 | P | PASS |
Jim Sly
|
|
|
Richard Phone #: ###-####
|
BLD-Footing | 4/21/2015 | 4/22/2015 | 4/22/2015 | A | PART |
Mike Jordan
|
|
|
Pour time at 1130. Top of the piers // Richard Phone #: ###-####0. work in progress. Noted that east and west footings have been deleted. Will need RFI from engineer of record.
|
BLD-Footing | 4/20/2015 | 4/21/2015 | 4/21/2015 | P | PART |
Jim Sly
|
|
|
late as possible Richard Phone #: ###-####bldg Select columns.... ok Bldg furthest East.
|
BLD-Footing | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Jim Sly
|
|
|
Richard-base of piers Phone #: ###-####-pour time 11:45 Building Furthest East. Talked to Engineer of Record. No special inspection required.
|