BLD-Final | 8/25/2015 | 8/25/2015 | 8/25/2015 | A | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Page
|
|
|
Previously noted items repaired, Life fire safety inspection passed/complete
|
BLD-Conference | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-####
|
BLD-Final | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### temp ok pending others
|
FIRE-Final Inspection | 8/19/2015 | 8/19/2015 | 8/19/2015 | P | FAIL |
Troy Cobbley
|
|
|
1) Breakroom 108 exit has been moved from interior doors to exterior door. Need approval with the 118 person occupant load. 2) Provide emergnecy light in Fire Pump Rm 3)Repair Emergency Lights in Locker Rms. 4) Provide signage at Fire Pump Rm. 5) Provide exit discharge lighting without photo cells and timers per discussion.
|
FIRE-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | CANC |
Jim Page
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PASS |
Jim Storey
|
|
|
Early afternoon - Lenard Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/5/2015 | 6/8/2015 | 6/8/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy
|
BLD-Framing/Rough-in | 5/8/2015 | 5/11/2015 | 5/11/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy alcoves ok to cover hanger side rated wall.
|
BLD-Wall cover | 4/24/2015 | 4/27/2015 | 4/27/2015 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy progression gyp ok hanger side/raised floor ok
|
BLD-Framing/Rough-in | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy hard ceillings and raised floor ok
|
BLD-Wall cover | 3/27/2015 | 3/30/2015 | 3/30/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy ok to cover office/ fire joint ok across hanger side.
|
BLD-Framing/Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy
|
BLD-Framing/Rough-in | 3/10/2015 | 3/10/2015 | 3/10/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy framing ok
|
BLD-Framing/Rough-in | 3/3/2015 | 3/4/2015 | 3/4/2015 | A | PASS |
Jim Storey
|
|
|
Framing / Firestopping Phone #: ###-#### Inspection requested via web by Brian Murphy end of 2hr and 1hr walls ok to cover.
|
BLD-Framing/Rough-in | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | PART |
Jim Storey
|
|
|
Brian Phone #: ###-#### review top of wall detail/ rfi to arch for wide flange perpendiclur penatratio. menbrane.
|