Permit Information
Permit NumberBLD14-03533
StatusFinaled
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 11789 W EXECUTIVE DR
Project NameDiversified Fluid Solutions
Customer Number 
ePlanReviewYes
Description
(DIVERSIFIED FLUID SOLUTIONS) //1-13-2020 There is a Men’s & Women’s restroom fixture ratio approval see attached document, any changes in workforce Men’s & Women’s percentages may require alterations to the restrooms. JG// **PRIORITY REVIEW** Remodel for new tenant with offices and industrial work areas in a 37,555 sq. ft. space per approved plans. Work to include removal and construction of new interior nonbearing partition walls new accessible restrooms in the fabrication area and a new unisex shower for the fabrication area, placement of a new RTU and the installation of miscelaneous equipment. No racking over 8 feet in height is allowed under this permit. This is a fully sprinklered building for area increase. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/17/20152/18/20152/18/2015APASS
DetailsMike Jordan
Dylan Phone #: ###-####. Ok for perm occ.
BLD-Final2/12/20152/13/20152/13/2015APART
DetailsMike Jordan
Dillion Phone #: ###-####. Ok for temp occ. Needs to provide ADA restroom sign provide flusher on toilet in mens restroom on turning side, Provide a high/low drinking fountain. A racking permit is also required.
FIRE-Final Inspection2/12/20152/12/20152/12/2015PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection2/10/20152/11/20152/11/2015AFAIL
DetailsTroy Cobbley
Provide the four exit discharge lights as per the approved plans.
FIRE-Sprinkler Rough-in2/9/20152/9/20152/9/2015PCANC
DetailsTroy Cobbley
wrong permit called in.
BLD-Ceiling Grid Inspection2/5/20152/5/20152/5/2015PPASS
DetailsMike Jordan
Dillon Phone #: ###-####
BLD-Ceiling Grid Inspection2/3/20152/4/20152/4/2015AFAIL
DetailsMike Jordan
Dillon Phone #: ###-####. Needs to provide clips on permiter to prevent the runners from spreading.
BLD-Framing/Rough-in1/13/20151/14/20151/14/2015APASS
DetailsMike Jordan
Dillion Phone #: ###-####. INterior steel stud framed walls for restroom package. Hardlids are ok, but still needs fire sprinkler rough in inspection.
BLD-Framing/Rough-in1/7/20151/7/20151/7/2015PPASS
DetailsMike Jordan
Dillon Phone #: ###-####. All interior steel stud framed walls except for restrooms ok. N o grid at this time.
BLD-Framing/Rough-in1/6/20151/7/20151/7/2015ANR
DetailsMike Jordan
Dillon Phone #: ###-####. No city approved plans. Electrical rough in completed. Ok to start one side with shhretrock. Contractor will recall inspection for this afternoon or tomorrow morning.