BLD-Final | 2/17/2015 | 2/18/2015 | 2/18/2015 | A | PASS |
Mike Jordan
|
|
|
Dylan Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 2/12/2015 | 2/13/2015 | 2/13/2015 | A | PART |
Mike Jordan
|
|
|
Dillion Phone #: ###-####. Ok for temp occ. Needs to provide ADA restroom sign provide flusher on toilet in mens restroom on turning side, Provide a high/low drinking fountain. A racking permit is also required.
|
FIRE-Final Inspection | 2/12/2015 | 2/12/2015 | 2/12/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 2/10/2015 | 2/11/2015 | 2/11/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide the four exit discharge lights as per the approved plans.
|
FIRE-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | CANC |
Troy Cobbley
|
|
|
wrong permit called in.
|
BLD-Ceiling Grid Inspection | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PASS |
Mike Jordan
|
|
|
Dillon Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | FAIL |
Mike Jordan
|
|
|
Dillon Phone #: ###-####. Needs to provide clips on permiter to prevent the runners from spreading.
|
BLD-Framing/Rough-in | 1/13/2015 | 1/14/2015 | 1/14/2015 | A | PASS |
Mike Jordan
|
|
|
Dillion Phone #: ###-####. INterior steel stud framed walls for restroom package. Hardlids are ok, but still needs fire sprinkler rough in inspection.
|
BLD-Framing/Rough-in | 1/7/2015 | 1/7/2015 | 1/7/2015 | P | PASS |
Mike Jordan
|
|
|
Dillon Phone #: ###-####. All interior steel stud framed walls except for restrooms ok. N o grid at this time.
|
BLD-Framing/Rough-in | 1/6/2015 | 1/7/2015 | 1/7/2015 | A | NR |
Mike Jordan
|
|
|
Dillon Phone #: ###-####. No city approved plans. Electrical rough in completed. Ok to start one side with shhretrock. Contractor will recall inspection for this afternoon or tomorrow morning.
|