BLD-Final | 9/29/2015 | 9/30/2015 | 9/30/2015 | A | PASS |
Jim Sly
|
|
|
Colyn Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 9/8/2015 | 9/8/2015 | 9/8/2015 | P | PASS |
Jim Sly
|
|
|
Colyn Phone #: ###-####
|
BLD-Framing/Rough-in | 8/5/2015 | 8/6/2015 | 8/6/2015 | A | PASS |
Jim Sly
|
|
|
Colyn-3rd floor Phone #: ###-####
|
BLD-Final | 5/29/2015 | 6/3/2015 | 6/3/2015 | A | PART |
Jim Sly
|
|
|
Colyn Phone #: ###-#### Temp Occ. OK.....Floors 1 and 2
|
FIRE-Final Inspection | 5/29/2015 | 6/2/2015 | 6/2/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy for the life safety is being given for the 1st and 2nd floors until the 3rd floor is complete. The door mags and the hvac shutdown, as previously discussed, needs to be addressed prior to a final sign off.
|
BLD-Ceiling Grid Inspection | 5/4/2015 | 5/4/2015 | 5/5/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | PART |
Jim Sly
|
|
|
Colyn Phone #: ###-#### OK to do perimeters and sprinkler penitrations. most lights are in and ok. Call back to inspect remaining lights.
|
BLD-Framing/Rough-in | 2/6/2015 | 2/6/2015 | 2/6/2015 | P | PART |
Jim Sly
|
|
|
Colyn Phone #: ###-#### 1st and 2nd floors only.....OK
|