Permit Information
Permit NumberBLD14-03688
StatusFinaled
Name HOFFMAN CONSTRUCTION COMPANY
Site Address 1099 W FRONT ST
Project NameSimplot Office Building
Customer Number 
ePlanReviewYes
Description
SIMPLOT OFFICE Tenant Improvement - This permit is to finish a new 306,345 square foot, nine story office building for occupancy. **Plan Modification 5/14/18 screens added to meet DR requirements, approved by engineer and DR**ajs****PLAN MODIFICATION 3-30-16 - Modification submitted to change the build out of the Lab space on the 5th floor. TLW** The first floor will have a large lobby area, customer experience area and office and training areas. There will be a wellness center at the south end of the main building. Separate tenant improvement permits will be required to finish the future coffee shop, incubator space and future restaurant at the first floor of the annex. The second floor of the main building will be office space. The second floor of the annex will have a large lobby, a multipurpose assembly room and an auditorium. The third floor of the main building will be office space. The fourth floor of the main building will be office space. The fourth floor of the annex is a restaurant with a full kitchen and large exterior patio seating area. The fifth floor of the main building will be office space. The fifth floor of the annex has a kitchen, office areas and a greenhouse. The greenhouse structure is deferred and has not been reviewed or approved. The sixth floor will be office space with an exterior deck at the south end of the floor. The seventh floor will be office space with a large conference room, a kitchen and exterior decks at the east and west ends of the floor. The eighth floor will be office space. The ninth floor will be office space. The core areas were completed under the shell and core permit BLD14-02173. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/31/20189/4/20189/4/2018PPASS
DetailsDave Hannah
Victoria Phone #: ###-####
FIRE-Final Inspection8/31/20189/4/20189/4/2018APASS
DetailsJim Page
Final life fire safety inspection complete.

Victoria Phone #: ###-####
BLD-Aging Inspection7/25/20187/25/20187/30/2018 PASS
DetailsDave Hannah
BLD-Aging Inspection5/25/20185/25/20185/30/2018 PEND
DetailsDave Hannah
DOC - Permit Expired3/16/20183/16/20183/16/2018ACANC
DetailsDave Hannah
BLD-Aging Inspection3/12/20183/12/20183/16/2018 PEND
DetailsDave Hannah
BLD-Final1/8/20181/9/20181/9/2018ANR
DetailsDave Hannah
Victoria Phone #: ###-####
BLD-Aging Inspection11/8/201711/8/201711/15/2017 PEND
DetailsDave Hannah
needs air seal and mec connection at stairs in garage
BLD-Aging Inspection8/28/20178/28/20178/29/2017 PEND
DetailsDave Hannah
FIRE-Final Inspection6/28/20176/28/20176/28/2017PPART
DetailsJim Page
Life fire safety inspection complete for SWHQ main building (to include level 5 lab area and fire command), baffles will be fabricated to prevent cold solder in the tasting room on level 5 of annex building. FIR15-00641 is attached to this projec in project related cases, this FIR permit will remain in issued status until courtyard area is complete. Fire panel for SWHQ builing is showing a ground fault, issue will need to be resolved before final life fire safety inspection for courtyard area. After mentioned items have passed inspection then life fire safety can be finalized.
BLD-Aging Inspection6/16/20176/16/20176/20/2017 PEND
DetailsDave Hannah
BLD-Aging Inspection3/27/20173/27/20173/28/2017 PEND
DetailsDave Hannah
BLD-Final1/23/20171/27/20171/27/2017APART
DetailsDave Hannah
Requesting TCO on office building levels 1-9. Phone #: ###-#### Inspection requested via web by Joe Borelli ok for temp occ
FIRE-Final Inspection1/24/20171/26/20171/26/2017PPART
DetailsJim Page
Egress lighting inspection complete for area's that sustained water damage.
FIRE-Final Inspection1/23/20171/24/20171/24/2017ACANC
DetailsJim Page
Egress/emergency lighting to be tested on 26JAN2017, this inspection request cancelled due to Simplot functions/personel that did not want to be interupted.
BLD-Final1/21/20171/25/20171/23/2017PCANC
DetailsDave Hannah
Requesting TCO update for office building levels 1-9. Phone #: ###-#### >> Inspection requested via web by Joe Borelli Inspection cancelled from web by: Joe Borelli
BLD-Final1/12/20171/13/20171/13/2017ANR
DetailsDave Hannah
Requesting TCO for Office Building Level 1 West Phone #: ###-#### Inspection requested via web by Joe Borelli
BLD-Final11/21/201611/22/201611/22/2016PPART
DetailsDave Hannah
Requesting TCO on levels 1-4 of Annex Phone #: ###-#### Inspection requested via web by Joe Borelli ok for temp occ
FIRE-Final Inspection11/21/201611/22/201611/22/2016PPART
DetailsJim Page
Fire sprinkler inspections are complete for annex levels 1 through 4, fire alarm inspections are complete for annex levels 1 through 4, fire extinguishers are in place with current inspection tags for annex levels 1 through 4, commercial hood suppression system inspections for annex level 4 kitchen are complete, exit/emergency egress lighting inspected for annex levels 1 through 4 complete. Partial life fire safety inspection for TCO complete for levels 1 through 4 of annex building.
BLD-Final11/21/201611/21/201611/22/2016ACANC
DetailsDave Hannah
Requesting TCO for levels 1-4 of Annex building Phone #: ###-#### Inspection requested via web by Joe Borelli
Extend Permit 90/180 days11/19/201611/21/201611/21/2016ACANC
DetailsDave Hannah
Requesting TCO for levels 1-4 of Annex building Phone #: ###-#### Inspection requested via web by Joe Borelli
BLD-Final11/17/201611/18/201611/21/2016PCANC
DetailsDave Hannah
Requesting TCO for levels 1-4 of Annex building Phone #: ###-#### Inspection requested via web by Joe Borelli
FIRE-Final Inspection11/17/201611/18/201611/18/2016PCANC
DetailsJim Page
Inspection request will be rescheduled.
BLD-Conference11/3/201611/4/201611/4/2016ADONE
DetailsDave Hannah
Requesting walk through and TCO status review of Annex building. Phone #: ###-#### Inspection requested via web by Joe Borelli
BLD-Final11/1/201611/2/201611/2/2016APART
DetailsDave Hannah
Requesting TCO for levels 1-9 of Office building. Phone #: ###-#### Inspection requested via web by Joe Borelli ok for temp occ on floors 1 thru 7 of office building
BLD-Final10/28/201610/28/201610/31/2016ANR
DetailsDave Hannah
Requesting final inspection for TCO of levels 1-9 of the Office building Phone #: ###-#### Inspection requested via web by Joe Borelli
BLD-Final10/26/201610/27/201610/28/2016ACANC
DetailsDave Hannah
Requesting final inspection for TCO of levels 1-9 of the Office building Phone #: ###-#### Inspection requested via web by Joe Borelli
Extend Permit 90/180 days10/28/201610/28/201610/28/2016ACANC
DetailsDave Hannah
Requesting final inspection for TCO of levels 1-9 of the Office building Phone #: ###-#### Inspection requested via web by Joe Borelli
FIRE-Final Inspection10/26/201610/27/201610/27/2016APART
DetailsJim Page
TCO authorized for levels 2 through 9 of Simplot World Headquarters as well as lobby section of level 1, final inspection for parking level and annex building to be completed at a later date. Fire alarm complete for level 1 lobby, levels 2 through 9 for TCO. Fire sprinklers complete for level 1 lobby, levels 2 through 9 for TCO. Fire extinguishers are in place with current inspection tags in mentioned area's. Partial life fire safety inspection complete for TCO in mentioned area's. Remaining inspections to be completed at a later date.
BLD-Framing/Rough-in7/8/20167/8/20167/8/2016APASS
DetailsDave Hannah
Ceiling framing inspection on level 7, stacks 3 and 4. Contact Steve Lawson ###-####.
BLD-Framing/Rough-in7/8/20167/8/20167/8/2016APASS
DetailsDave Hannah
Interior framing level 9. Contact John Woods ###-####.
BLD-Framing/Rough-in7/8/20167/8/20167/8/2016APASS
DetailsDave Hannah
Ceiling framing inspection for all of level 6 for anytime this morning. Call Steve Lawson ###-####.