BLD-Aging Inspection | 8/30/2017 | 8/30/2017 | 8/30/2017 | | PEND |
Mike Jordan
|
|
|
Building is complete, all issues were resolved. Either needs to pick up c.o. or needs to satisfy other dept. sign offs.
|
BLD-Aging Inspection | 6/30/2017 | 6/30/2017 | 6/30/2017 | | PASS |
Mike Jordan
|
|
|
Needs to pick up c. o.
|
BLD-Final | 2/15/2017 | 2/16/2017 | 2/16/2017 | P | PASS |
Mike Jordan
|
|
|
Clintun Phone #: ###-####. Ok for perm occ. when ACHD and PW do their finals
|
BLD-Final | 10/14/2016 | 10/17/2016 | 10/17/2016 | A | PEND |
Mike Jordan
|
|
|
Please call ahead for access - Dave Phone #: ###-####. Spoke with Dave, waiting for furniture plan to be submitted for review and approval.
|
FIRE-Final Inspection | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. I suggested that the recycle bin next to the FDC be relocated to give fire personell more room to work.
|
FIRE-Final Inspection | 9/23/2016 | 9/27/2016 | 9/27/2016 | P | CANC |
Jim Page
|
|
|
Tried calling points of contact, Quenton ###-#### and Paul ###-####, did not receive a call back from either contact, this inspection request cancelled due to no return phone call and a new inspection request will need to be rescheduled.
|
FIRE-Final Inspection | 7/27/2016 | 7/29/2016 | 7/29/2016 | P | CANC |
Troy Cobbley
|
|
|
Clinton Phone #: ###-####
|
FIRE-Final Inspection | 7/27/2016 | 7/28/2016 | 7/28/2016 | P | NR |
Troy Cobbley
|
|
|
Need the city approved plans to verify the fire dept access. I did a drive by and noted care blocking access on the west and north sides of the building.
|
BLD-Final | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | NR |
Mike Jordan
|
|
|
Quiton Phone #: ###-####
|
BLD-Final | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PART |
Mike Jordan
|
|
|
Contact Tony Phone #: ###-#### Inspection requested via web by Tony Inserra. Ok for temp. occ. only.
|
FIRE-Final Inspection | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy for life safety is being given until the scope of work has been complete. Currently the existing building/dealership has not been demolished and the parking lot/fire lane completed. Contractor is hoping with in the next 6 weeks all work will be complete.
|
FIRE-Final Inspection | 11/4/2015 | 11/5/2015 | 11/5/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire dept review comments, provide the additioanl four fire extinguishers, provide the two additional exit discharge lights and repair the two non-functional emergency lights, replace the bent sprinkler hanger rod and provide cages for the upright heads underneath the stairs. Provide fire dept access around the north side of the building per the approved plans.
|
BLD-Conference | 11/2/2015 | 11/3/2015 | 11/3/2015 | A | CANC |
Mike Jordan
|
|
|
Pree-walk for final inspection. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Conference | 11/3/2015 | 11/3/2015 | 11/3/2015 | P | DONE |
Mike Jordan
|
|
|
Pre walk through with contractor. Needs zoning sign off. Appears that furniture plans was not submited and reviewed for ADA compliance. Noted door hardware issues as well.
|
FIRE-Conference | 10/26/2015 | 10/26/2015 | 10/27/2015 | P | DONE |
Troy Cobbley
|
|
|
I performed a walk through with Tony and discussed door hardware issues on several of the doors that are utilizing thumb turn dead bolts on interior doors.
|
BLD-Ceiling Grid Inspection | 10/21/2015 | 10/21/2015 | 10/21/2015 | A | PASS |
Mike Jordan
|
|
|
Ceiling grid inspection requested by Tony. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Ceiling Grid Inspection | 10/9/2015 | 10/12/2015 | 10/12/2015 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/6/2015 | 10/7/2015 | 10/7/2015 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Ceiling grid at service bay and break room ok.
|
BLD-Framing/Rough-in | 9/10/2015 | 9/11/2015 | 9/11/2015 | A | PASS |
Mike Jordan
|
|
|
Tracey Phone #: ###-####. Interior steel stud walls for insuarance and finance offices and vehicle delivery area.
|
BLD-Energy code compliance | 9/8/2015 | 9/9/2015 | 9/9/2015 | P | PART |
Jim Sly
|
|
|
Tony Phone #: ###-#### E. W. and S. walls showroom.
|
BLD-Framing/Rough-in | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Exterior steel stud wall framing and soffits at showroom. Interior steel stud framed walls and soffits at showroom, showroom ofices, conferance room and back offices.
|
BLD-Framing/Rough-in | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Interior steel stud framed walls and hardlids for showroom restrooms ok to cover.
|
BLD-Conference | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | DONE |
Mike Jordan
|
|
|
Job site visit. Check special inspection reports, job status. Contractor has begun interior framing and exterior framing of steel stud walls and soffits. Reviewed approved plans.
|
BLD-Foundation | 6/23/2015 | 6/24/2015 | 6/24/2015 | A | PART |
Mike Jordan
|
|
|
CMU pour time 1:00PM; Tony ###-####. Work in progress, pend. special inspection. Also reviewed special inspection check sheet.
|
BLD-Foundation | 6/23/2015 | 6/23/2015 | 6/23/2015 | P | NR |
Tony Young
|
|
|
###-####-Tony-CMU-pour at 1:00
|
BLD-Foundation | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU 1:00PM pour; Tony Phone #: ###-####
|
BLD-Foundation | 6/4/2015 | 6/4/2015 | 6/4/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU 1:00PM pour; Tony Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU pour time 1:00PM; Tony Phone #: ###-####. Special inspetor on site.
|
BLD-Foundation | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | DEFR |
Mike Jordan
|
|
|
CMU Grout 1PM, MTI will be out as well - Tony Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | DEFR |
Phil Shearer
|
|
|
|
BLD-Foundation | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | DEFR |
Mike Jordan
|
|
|
Tony Phone #: ###-####
|
BLD-Foundation | 5/18/2015 | 5/18/2015 | 5/18/2015 | P | DEFR |
Mike Jordan
|
|
|
Tony Phone #: ###-####. grout placement completed. Special inspector on site.
|
BLD-Foundation | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PART |
Mike Jordan
|
|
|
CMU grout pour 2:00PM; Tony Phone #: ###-####. Top of footing to finish floor elevation, work in progress, special inspector on site.
|
BLD-Foundation | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | DEFR |
Mike Jordan
|
|
|
Tony-cmu-pour time 2:00 Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 5/12/2015 | 5/12/2015 | 5/12/2015 | P | PART |
Mike Jordan
|
|
|
CMU, pour time 2:00PM; Tony Phone #: ###-####. masonry wall on gridline 1.3, top of footong to finish floor elevation. Work in progress, special inspector on site.
|
BLD-Foundation | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | CANC |
Phil Shearer
|
|
|
Grout pour time 2:00PM; Rudy Phone #: ###-####
|
BLD-Foundation | 5/7/2015 | 5/8/2015 | 5/8/2015 | P | PART |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Masonry wall, top of footing to finish floor elevation at demissing wall between showroom and service bays.
|
BLD-Footing | 5/7/2015 | 5/8/2015 | 5/8/2015 | A | PASS |
Mike Jordan
|
|
|
Tony// pour time is 1030 Phone #: ###-####. Interior column pad footings and interior footings at showroom and service bays. All previous issues have been resolved.
|
BLD-Foundation | 4/29/2015 | 4/30/2015 | 4/30/2015 | A | FAIL |
Mike Jordan
|
|
|
Tony Phone #: ###-####. No city approved plans on site, Special inspector on jobsite ni ICC certified.
|