Permit Information
Permit NumberBLD15-00296
StatusFinaled
Name SAUCERMAN CONSTRUCTION
Site Address 818 W IDAHO ST
Project NameLunchBOX
Customer Number 
ePlanReviewYes
Description
(LUNCHBOX) The fire sprinkler system is used for building area increase, for story increase, and for fire area. To remodel an existing building for a new full-service, speed-wax salon and office tenant. The basement has a floor area of about 1,888 square feet and is NOT approved for occupancy (considered to be an unoccupied crawlspace having some mechanical equipment). The wax salon is located on the 1st story and has a floor area of about 2,029 square feet. The 2nd story has a floor area of about 4,382 square feet and will have a reception area, waiting areas, offices, and a conference room. Work includes interior nonbearing walls, 3 single user restrooms accessible to the disabled, interior doors, interior windows, suspended acoustical ceilings, gypsum board ceilings, millwork, finishes, exterior storefront glazing, exterior windows, exterior doors, and exterior plaster. An elevator will be installed in conjunction with this permit. Structural work that was started about 5 years ago without a permit will be completed under this permit. Structural work includes new joists attached to existing joists, new beams, new beam hangers, new columns, concrete anchors, and a steel pan deck to support a new concrete slab. Special Inspection is required for epoxy anchors, for Titen anchors, and for welding. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 (including quick-response sprinklers where required) and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/18/20158/18/20158/18/2015PPASS
DetailsDave Hannah
Requested by Shane Treasure Phone #: ###-#### Inspection requested via web by Shane Treasure
FIRE-Final Inspection8/17/20158/18/20158/18/2015APASS
DetailsJim Page
Life fire safety passed/complete
FIRE-Final Inspection8/17/20158/17/20158/17/2015PCANC
DetailsJim Page
Fire life safety inspection Shane Treasure Phone #: ###-#### >> Inspection requested via web by Shane Treasure Inspection cancelled from web by: Shane Treasure
BLD-Ceiling Grid Inspection8/3/20158/4/20158/4/2015PPASS
DetailsDave Hannah
Rich Phone #: ###-####
BLD-Framing/Rough-in7/20/20157/21/20157/22/2015PPASS
DetailsDave Hannah
First floor lobby framing inspection Phone #: ###-#### Inspection requested via web by Shane Treasure
BLD-Conference7/20/20157/21/20157/20/2015PCANC
DetailsDave Hannah
Lobby framing inspection Phone #: ###-#### >> Inspection requested via web by Shane Treasure Inspection cancelled from web by: Shane Treasure
BLD-Concrete7/9/20157/13/20157/13/2015APASS
DetailsDave Hannah
New pan deck for inspection Phone #: ###-#### Inspection requested via web by Shane Treasure
BLD-Ceiling Grid Inspection6/30/20157/1/20157/1/2015APASS
DetailsDave Hannah
Inspection
Shane Treasure Phone #: ###-#### Inspection requested via web by Shane Treasure
BLD-Framing/Rough-in6/4/20156/5/20156/5/2015PPASS
DetailsDave Hannah
Framing inspection for stairways and first floor except front lobby Phone #: ###-#### Inspection requested via web by Shane Treasure
BLD-Conference5/27/20155/27/20155/27/2015PPEND
DetailsTony Young
First floor alley egress design
Shane Treasure Phone #: ###-#### Inspection requested via web by Shane Treasure,,, referred to plan review
BLD-Energy code compliance5/21/20155/22/20155/22/2015APART
DetailsTony Young
Second floor insulation Phone #: ###-#### Inspection requested via web by Shane Treasure,, walls ok to cover on 2nd floor
BLD-Framing/Rough-in5/13/20155/14/20155/14/2015APART
DetailsDave Hannah
Structural improvements and second floor framing for cover
Shane Treasure
Phone #: ###-#### Inspection requested via web by Shane Treasure second frool and basement ok
BLD-Framing/Rough-in5/12/20155/13/20155/13/2015PCANC
DetailsDave Hannah
Structural framing improvement in basement and second floor.
Shane Treasure Phone #: ###-#### >> Inspection requested via web by Shane Treasure Inspection cancelled from web by: Shane Treasure