FIRE-Final Inspection | 7/7/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-#### final ok pending fire sign off for pull station
|
FIRE-Final Inspection | 6/29/2015 | 6/30/2015 | 6/30/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until the existing manual pull station has been relocated back to its original position. All other life safety items appear ok.
|
BLD-Ceiling Grid Inspection | 6/1/2015 | 6/2/2015 | 6/2/2015 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
FIRE-Conference | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | DONE |
Katie Marron
|
|
|
Fire conference on relocation of existing fire extinguisher and pull station per note on plans. Existing fire extinguisher cabinet placement is still acceptable. Fire pull to move to adjacent wall and to the side of fire extinguisher cabinet.
|
BLD-Framing/Rough-in | 5/4/2015 | 5/6/2015 | 5/6/2015 | A | PASS |
Jim Storey
|
|
|
Call 5 min before to be let in // John Phone #: ###-####
|