BLD-Final | 8/7/2015 | 8/10/2015 | 8/10/2015 | A | PASS |
Mike Jordan
|
|
|
Won''t in until 9 // Brad Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | NR |
Jim Sly
|
|
|
Jeff Phone #: ###-#### C/N need many signatures....
|
FIRE-Final Inspection | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Wall Bracing | 7/7/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Jim Sly
|
|
|
Jeff Phone #: ###-####
|
BLD-Energy code compliance | 7/2/2015 | 7/2/2015 | 7/2/2015 | P | PART |
Jim Sly
|
|
|
Sean Phone #: ###-#### Still need to see brace panel S. wall. Insulation .....OK
|
BLD-Framing/Rough-in | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Jim Sly
|
|
|
Sean Phone #: ###-####
|
BLD-Wall Bracing | 6/23/2015 | 6/24/2015 | 6/24/2015 | A | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Ext. nailing OK. Still need to see brace panel at South wall.
|
BLD-Wall Bracing | 6/16/2015 | 6/17/2015 | 6/17/2015 | A | FAIL |
Jim Sly
|
|
|
Jeff-plans inside on table Phone #: ###-#### More nailing and Brace panel at S. wall.
|
BLD-Wall Bracing | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### FOUNDATION WALL OK
|
BLD-Footing | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | PASS |
Jim Sly
|
|
|
David Phone #: ###-####
|
BLD-Footing | 5/14/2015 | 5/15/2015 | 5/15/2015 | A | FAIL |
Jim Storey
|
|
|
As early as possible // David Phone #: ###-#### remove water
|
BLD-Conference | 5/8/2015 | 5/11/2015 | 5/11/2015 | A | DONE |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Called Sarah McClendon Struct Eng. She says no Req. For special inspection. Contr to order 3500 PSI mud for footing/walls .....4000 for slab. Concrete Contr. Notified.
|