BLD-Final | 12/30/2015 | 12/31/2015 | 12/31/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once public works signs perm.
|
BLD-Final | 12/30/2015 | 12/30/2015 | 12/30/2015 | P | NR |
Dave Hannah
|
|
|
Brent Phone #: ###-#### walked project with con
|
FIRE-Final Inspection | 12/23/2015 | 12/24/2015 | 12/24/2015 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, Smoke alarms appear to be stand alone, no fire alarm panel/FIR permits. Life fire safety inspection passed/complete
|
BLD-Ceiling Grid Inspection | 12/16/2015 | 12/17/2015 | 12/17/2015 | P | PASS |
Jim Sly
|
|
|
Brent Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. East offices only ok.
|
BLD-Conference | 12/7/2015 | 12/8/2015 | 12/8/2015 | A | NR |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Remove pop rivets from grid.
|
BLD-Other | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Mike Jordan
|
|
|
Fire wall // Brent Phone #: ###-####
|
BLD-Conference | 11/23/2015 | 11/24/2015 | 11/24/2015 | A | DONE |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Wwent over rated penetrations requirements on 1hr. wall.
|
BLD-Wall cover | 11/20/2015 | 11/20/2015 | 11/20/2015 | P | DONE |
Jim Sly
|
|
|
dry wall // Brent Phone #: ###-#### Drywall attachment 1 hr wall at Electrical room ....OK.
|
BLD-Energy code compliance | 11/12/2015 | 11/13/2015 | 11/13/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####
|
BLD-Framing/Rough-in | 11/9/2015 | 11/10/2015 | 11/10/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. INterior steel stud framed walls ok and hard lids.
|
BLD-Framing/Rough-in | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Interior steel stud fur out framed wall in electrical room ok.
|
BLD-Energy code compliance | 10/7/2015 | 10/7/2015 | 10/8/2015 | P | PASS |
Mike Jordan
|
|
|
Insulation // Brent Phone #: ###-####
|
BLD-Framing/Rough-in | 9/24/2015 | 9/25/2015 | 9/25/2015 | A | PART |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Steel decking and joist welding at office area. Noted areas to be repaired. These areas also noted on special inspection report. Ok to insulate after special inspection has passed. Joist to imbed connections ok to insulate.
|
BLD-Foundation | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | PART |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Pend. special inspection.
|
BLD-Footing | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Column pad footings for pay canopy. Footings for trash enclosure ok.
|
BLD-Other | 8/26/2015 | 8/27/2015 | 8/27/2015 | P | PASS |
Mike Jordan
|
|
|
slab // Brent Phone #: ###-####. Topping slab over hollow panels for roof ok.
|
BLD-Foundation | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Mike Jordan
|
|
|
Wall // Brent Phone #: ###-####
|
BLD-Footing | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | PART |
Mike Jordan
|
|
|
Brent Phone #: ###-####. nterior footings and silicon trash pits. Work in progress. Special inspector on site.
|
BLD-Footing | 7/27/2015 | 7/28/2015 | 7/28/2015 | P | DEFR |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Pending special inspection.
|
BLD-Foundation | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. Concrete stemwall for conveyor trench.
|
BLD-Foundation | 7/16/2015 | 7/17/2015 | 7/17/2015 | P | PART |
Jim Sly
|
|
|
Brent-rebar Phone #: ###-#### Concrete Tilt Up walls .....#s 11 thru 13 16 thru 20 and 33 thru 37 OK pending Terricon Special inspection, tests and approvals.
|
BLD-Foundation | 7/15/2015 | 7/16/2015 | 7/16/2015 | P | PASS |
Mike Jordan
|
|
|
Rebar // Brent Phone #: ###-####. Concrete tilt panels ok.
|
BLD-Foundation | 7/13/2015 | 7/14/2015 | 7/14/2015 | P | PASS |
Mike Jordan
|
|
|
Rebar; Brent Phone #: ###-####. All previous ftilt panels that failed have been repaired. ok for concrete.
|
BLD-Foundation | 7/13/2015 | 7/13/2015 | 7/13/2015 | P | FAIL |
Mike Jordan
|
|
|
Brent-wall (tilt up) Phone #: ###-####. Concrete tilt panels, panels inspected noted missing perimeter rebar, incorrect grid spacing of rebar and incorrect lap lengths.
|
BLD-Concrete | 7/7/2015 | 7/9/2015 | 7/9/2015 | P | PART |
Mike Jordan
|
|
|
3 - 4 pm please for Tilt up walls - Brent Phone #: ###-####. Work in progress on concrete tilt panels. Special inspector on site.
|
BLD-Footing | 7/6/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Mike Jordan
|
|
|
Brent Phone #: ###-####. North perimeter footing ok.
|