BLD-Final | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton OK for Perm Occ.
|
BLD-Final | 8/18/2015 | 8/19/2015 | 8/19/2015 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Needs plumbing final.
|
FIRE-Final Inspection | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PART |
Mike Jordan
|
|
|
Later morning if possible. Phone #: ###-#### Inspection requested via web by Darius Saxton. Majority of the work has been completed. Needs to final out the project related fire sprinkler permit and needs fire/life/safety final.
|
FIRE-Final Inspection | 8/4/2015 | 8/5/2015 | 8/5/2015 | A | PART |
Jim Page
|
|
|
Life fire safety inspection passed/complete for room 2. Checked the FIR permit for the sprinklers, it was not finaled at time of inspection, was informed by onsite point of contact, Darius phone ###-#### that the contractor is working to get some as builds provided for fire sprinkler work, cannot final life fire and safety until sprinkler FIR is finaled.
|
BLD-Ceiling Grid Inspection | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Final | 6/12/2015 | 6/12/2015 | 6/12/2015 | P | PART |
Mike Jordan
|
|
|
Bi-Plane Phase 1 Phone #: ###-#### Inspection requested via web by Darius Saxton. phase ok. counter top height needs to be lowered to 34 inches in rm #101.
|
FIRE-Final Inspection | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in rooms 6, 101 and 102
|
BLD-Ceiling Grid Inspection | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok pend. mech.
|
BLD-Framing/Rough-in | 5/13/2015 | 5/14/2015 | 5/14/2015 | A | PASS |
Mike Jordan
|
|
|
Radiology room 6 rough-in. Phone #: ###-#### Inspection requested via web by Darius Saxton. All previous issues have been resolved. ok for cover.
|
BLD-Framing/Rough-in | 5/4/2015 | 5/5/2015 | 5/5/2015 | A | PART |
Mike Jordan
|
|
|
This project is in phases. This would be for small office/ break room for phase 1. Darius Saxton Phone #: ###-#### Inspection requested via web by Brad Turk. Interior steel stud framed walls for phase 1 work. Noted that an interior 5" x 5" tube steel coulmn has been found that was not noted on plans, architect to provide a listed assembly for colomn. Aslo noted at radiology room remodel that interior portion of existing corridor is not maintained. Addtional 5/8" type rock will need o be installed.
|