Permit Information
Permit NumberBLD15-00788
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 1055 N CURTIS RD
Project NameSARMC
Customer Number 
ePlanReviewNo
Description
(ST. AL’S RADIOLOGY BI-PLANE REMODEL – 1 STORY PORTION LOCATED SOUTH OF THE SOUTH TOWER) Fire sprinkler system used for high-rise and for occupancy. To remodel 3 areas located within the one story portion of the building located South of the South Tower (357 square feet, 1,674 square feet, and 472 square feet) of the Saint Alphonsus Regional Medical Center. New radiology bi-plane equipment will replace existing equipment. Except for a new door in an existing smoke partition, no fire barriers, smoke barriers, or smoke partitions are affected by this remodel. Work is to include upgrading an existing restroom to be more accessible to the disabled, interior nonbearing walls, suspended acoustical ceilings, suspended acoustical ceiling using a “Unistrut” framework, gypsum board soffits, a modified utility trench in the floor, footings to support new equipment, a concrete mechanical pad for UPS equipment located on the 2nd story in close proximity to the bi-plane room located on the 1st story, millwork, and finishes. The floor of the radiology bi-plane room is expected to be a concrete slab on grade without a basement below. Structural work includes concrete footings to support the bi-plane device and a concrete footing to support the patient table. Special Inspection is required for concrete, welding, expansion anchors, epoxy anchors, and other post-installed concrete anchors. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/2/201510/2/201510/2/2015PPASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Darius Saxton
OK for Perm Occ.
BLD-Final8/18/20158/19/20158/19/2015PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Needs plumbing final.
FIRE-Final Inspection8/18/20158/19/20158/19/2015APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final8/4/20158/5/20158/5/2015APART
DetailsMike Jordan
Later morning if possible. Phone #: ###-#### Inspection requested via web by Darius Saxton. Majority of the work has been completed. Needs to final out the project related fire sprinkler permit and needs fire/life/safety final.
FIRE-Final Inspection8/4/20158/5/20158/5/2015APART
DetailsJim Page
Life fire safety inspection passed/complete for room 2. Checked the FIR permit for the sprinklers, it was not finaled at time of inspection, was informed by onsite point of contact, Darius phone ###-#### that the contractor is working to get some as builds provided for fire sprinkler work, cannot final life fire and safety until sprinkler FIR is finaled.
BLD-Ceiling Grid Inspection7/15/20157/16/20157/16/2015APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton
BLD-Final6/12/20156/12/20156/12/2015PPART
DetailsMike Jordan
Bi-Plane Phase 1 Phone #: ###-#### Inspection requested via web by Darius Saxton. phase ok. counter top height needs to be lowered to 34 inches in rm #101.
FIRE-Final Inspection6/10/20156/11/20156/11/2015APART
DetailsTroy Cobbley
Life safety passed in rooms 6, 101 and 102
BLD-Ceiling Grid Inspection6/4/20156/5/20156/5/2015APART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok pend. mech.
BLD-Framing/Rough-in5/13/20155/14/20155/14/2015APASS
DetailsMike Jordan
Radiology room 6 rough-in. Phone #: ###-#### Inspection requested via web by Darius Saxton. All previous issues have been resolved. ok for cover.
BLD-Framing/Rough-in5/4/20155/5/20155/5/2015APART
DetailsMike Jordan
This project is in phases. This would be for small office/ break room for phase 1. Darius Saxton Phone #: ###-#### Inspection requested via web by Brad Turk. Interior steel stud framed walls for phase 1 work. Noted that an interior 5" x 5" tube steel coulmn has been found that was not noted on plans, architect to provide a listed assembly for colomn. Aslo noted at radiology room remodel that interior portion of existing corridor is not maintained. Addtional 5/8" type rock will need o be installed.