BLD-Final | 10/31/2016 | 10/31/2016 | 11/2/2016 | P | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-#### OK for Perm Occ. (sorry....he didn't have card)
|
FIRE-Final Inspection | 11/2/2016 | 11/3/2016 | 11/2/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | FAIL |
Troy Cobbley
|
|
|
Still need the emergency light on the second floor northwest corner repaired. All other items have been corrected.
|
FIRE-Final Inspection | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | FAIL |
Troy Cobbley
|
|
|
Provide correct building address for the fire alarm monitoring, repair three emergency lights, install the missing exit sign, provide fire dept access signage. Per contractor the shown gate/fencing will not be installed.
|
BLD-Ceiling Grid Inspection | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | PASS |
Jim Sly
|
|
|
Keagan Phone #: ###-####
|
FIRE-Conference | 9/15/2016 | 9/15/2016 | 9/15/2016 | A | DONE |
Katie Marron
|
|
|
Phone call with Jake on where Knox box should be installed (entrance or riser room). Advised it should be installed by where the fire alarm panel will be which is he said is the main entrance.
|
BLD-Framing/Rough-in | 8/31/2016 | 9/1/2016 | 9/2/2016 | P | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-####
|
FIRE-Conference | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | DONE |
Troy Cobbley
|
|
|
Jake Phone #: ###-####
|
BLD-Energy code compliance | 8/18/2016 | 8/18/2016 | 8/19/2016 | P | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### West wall 2nd floor OK.
|
BLD-Energy code compliance | 8/10/2016 | 8/11/2016 | 8/11/2016 | A | PART |
Jim Sly
|
|
|
Insulation // Jake Phone #: ###-#### South Wall 2nd floor...OK.
|
BLD-Energy code compliance | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### Select walls ....OK
|
BLD-Energy code compliance | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### West wall 1st floor.......OK
|
BLD-Energy code compliance | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | NR |
Jim Sly
|
|
|
Please call ahead for access - Jake Phone #: ###-####
|
BLD-Other | 6/17/2016 | 6/20/2016 | 6/20/2016 | P | PART |
Jim Storey
|
|
|
Jake-steel deck-concrete Phone #: ###-####wip
|
BLD-Conference | 5/10/2016 | 5/10/2016 | 5/10/2016 | P | DONE |
Jim Sly
|
|
|
Jake Phone #: ###-####
|
BLD-Footing | 3/22/2016 | 3/23/2016 | 3/23/2016 | A | PART |
Jim Sly
|
|
|
Late morning // Jake Phone #: ###-#### Special insp Required .......Footing pads at East and West walls of Bldg.......and just S. of Elevator. Elevator footing. OK pending MTI special inspections, tests and approvals.
|