Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberBLD15-00907
StatusFinaled
Name JSE ENTERPRISES LLC
Site Address 6903 W TARGEE ST
Project NameSun Valley Express Facility
Customer Number 
ePlanReviewYes
Description
(SUN VALLEY EXPRESS FACILITY)Permit for a new 5,916 sq.ft. bus maintenance building and associated site work. A 3 hour fire barrier will be constructed to create a 4,925 sq ft commercial bus repair/maintenance and wash bay separate from the remainder of the building. Limiting the square footage to under 5,000 per IBC 903.2.9.1 #4 exempts the requirements for fire sprinklers in commercial auto repair area. This building is not fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/3/20171/4/20171/4/2017APASS
DetailsPhil Shearer
To close out - BND15-00121 completed 7/5/16 Phone #: ###-####
BLD-Final1/3/20171/3/20171/3/2017PCANC
DetailsPhil Shearer
BLD-Aging Inspection4/15/20164/15/20164/15/2016 PEND
DetailsPhil Shearer
BLD-Aging Inspection4/14/20164/14/20164/15/2016 PEND
DetailsPhil Shearer
BLD-Final12/1/201512/1/201512/2/2015PPART
DetailsPhil Shearer
Jeff Phone #: ###-#### OK for temp
BLD-Final11/25/201511/27/201511/27/2015ANR
DetailsPhil Shearer
JC Phone #: ###-####
FIRE-Final Inspection11/25/201511/25/201511/25/2015PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Energy code compliance11/2/201511/2/201511/2/2015PPASS
DetailsPhil Shearer
Jeff Phone #: ###-####
BLD-Energy code compliance10/29/201510/29/201510/29/2015PPART
DetailsPhil Shearer
Insulation // Jeff Phone #: ###-####. Air seal OK
BLD-Framing/Rough-in10/29/201510/29/201510/29/2015PPASS
DetailsPhil Shearer
Insulation // Jeff Phone #: ###-####
BLD-Wall Bracing10/5/201510/6/201510/6/2015APASS
DetailsPhil Shearer
Shear // Jafe Phone #: ###-####
BLD-Other9/24/20159/24/20159/24/2015PPART
DetailsJim Storey
FIre barrier wall - Jeff Phone #: ###-#### screw sch ok inside room north.
BLD-Foundation8/6/20158/7/20158/7/2015APASS
DetailsPhil Shearer
retaining wall; Jed Phone #: ###-####
BLD-Footing8/4/20158/4/20158/4/2015PPASS
DetailsPhil Shearer
interior; Jeff Phone #: ###-####
BLD-Concrete7/9/20157/9/20157/9/2015PPASS
DetailsPhil Shearer
Jeff Phone #: ###-####
BLD-Footing7/7/20157/8/20157/8/2015PPASS
DetailsJim Sly
Jay Phone #: ###-####