BLD-Final | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
FIRE-Final Inspection | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags, knox box is mounted next to fire sprinkler riser room, signage for fire sprinkler riser room will be installed afetr door is painted. Final life fire safety inspection passed/complete.
|
BLD-Energy code compliance | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PASS |
Tony Young
|
|
|
1st floor // Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 6/2/2017 | 6/5/2017 | 6/5/2017 | A | PART |
Tony Young
|
|
|
First floor // Ed Phone #: ###-####,, drop areas ok
|
BLD-Energy code compliance | 5/22/2017 | 5/22/2017 | 5/23/2017 | P | PASS |
Tony Young
|
|
|
2nd floor // Ed Phone #: ###-####
|
BLD-Other | 5/18/2017 | 5/19/2017 | 5/19/2017 | A | PART |
Tony Young
|
|
|
2nd // Ed Phone #: ###-####,, fire caulking done,, need one more layer of rock in the chase lid
|
BLD-Framing/Rough-in | 5/18/2017 | 5/19/2017 | 5/19/2017 | A | PART |
Tony Young
|
|
|
2nd floor - Ed Phone #: ###-####,, ok to insulate
|
BLD-Energy code compliance | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PASS |
Tony Young
|
|
|
Ed-3rd floor Phone #: ###-####
|
BLD-Footing | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PART |
Tony Young
|
|
|
Ed-play ground equipment Phone #: ###-####,, special inspector on site,, 4 pad footings
|
BLD-Energy code compliance | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PART |
Tony Young
|
|
|
Ed-3rd floor Phone #: ###-####,, floor ceiling ok
|
BLD-Framing/Rough-in | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PART |
Tony Young
|
|
|
Ed-3rd floor Phone #: ###-####,, 3rd floor ok to insulate,, ceiling/floor ok to cover
|
BLD-Energy code compliance | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | PART |
Tony Young
|
|
|
4th floor - Ed Phone #: ###-####,, 4th ok
|
BLD-Framing/Rough-in | 5/2/2017 | 5/3/2017 | 5/3/2017 | P | PASS |
Tony Young
|
|
|
Ed-4th floor Phone #: ###-####,, ok to insulate
|
BLD-Other | 5/2/2017 | 5/3/2017 | 5/3/2017 | A | PEND |
Tony Young
|
|
|
Ed-tinting Phone #: ###-####-4th floor,, need fire sprinkler insp
|
BLD-Other | 4/26/2017 | 4/27/2017 | 4/27/2017 | P | PASS |
Jim Sly
|
|
|
Fire caulking & framing level 3 - Ed Phone #: ###-####
|
BLD-Other | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PART |
Tony Young
|
|
|
Fire caulking & framing level 2 and 3 - Ed Phone #: ###-####/// level 2 ok to insulate pre-rock areas,, 3 is not ready
|
BLD-Other | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | NR |
Tony Young
|
|
|
Fire caulking & framing level 2 and 3 - Ed Phone #: ###-####
|
BLD-Other | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | PART |
Tony Young
|
|
|
Fire caulking & framing - Ed Phone #: ###-####,, 1st floor ok to insulate now
|
BLD-Other | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | NR |
Tony Young
|
|
|
Fire caulking & framing - Ed Phone #: ###-####,, walk through,, still missing some areas
|
BLD-Other | 4/21/2017 | 4/24/2017 | 4/24/2017 | A | NR |
Tony Young
|
|
|
Fire caulking & framing - Ed Phone #: ###-####
|
BLD-Other | 4/21/2017 | 4/21/2017 | 4/24/2017 | P | NR |
Tony Young
|
|
|
Fire caulking & framing - Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 4/20/2017 | 4/21/2017 | 4/21/2017 | A | NR |
Tony Young
|
|
|
Fire caulking & framing - Ed Phone #: ###-####,, pre rock areas,, not ready,, need to re-fire caulk properly
|
BLD-Framing/Rough-in | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | DEFR |
Tony Young
|
|
|
Fire caulking & framing - Ed Phone #: ###-####
|
BLD-Energy code compliance | 2/23/2017 | 2/24/2017 | 2/24/2017 | P | CANC |
Tony Young
|
|
|
Ed//Shear inspection Phone #: ###-####
|
BLD-Wall Bracing | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | CANC |
Tony Young
|
|
|
Ed//Shear inspection Phone #: ###-####
|
BLD-Framing/Rough-in | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | PART |
Tony Young
|
|
|
Ed//Shear inspection Phone #: ###-####,, exterior shear ok after nailing marked areas
|
BLD-Energy code compliance | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | PASS |
Jim Sly
|
|
|
Insulation plumbing walls // Ed Phone #: ###-####
|
BLD-Wall Bracing | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | PART |
Jim Sly
|
|
|
Shear // Ed Phone #: ###-#### INTERIOR
|
BLD-Other | 2/3/2017 | 2/6/2017 | 2/6/2017 | A | PART |
Tony Young
|
|
|
Roof nailing - Ed Phone #: ###-####,, no inspection made,, weather and 4 story issues,, ok pending self certification
|