BLD-Final | 8/11/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Mike Jordan
|
|
|
Please call for access. Thanks Phone #: ###-#### Inspection requested via web by matthew greenman. OK for perm occ. No mech. work. Ceiling grid and diffusers remained in place.
|
FIRE-Final Inspection | 8/11/2015 | 8/12/2015 | 8/12/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/10/2015 | 8/11/2015 | 8/11/2015 | A | CANC |
Katie Marron
|
|
|
Rescheduled in order to have personnel on site to test smoke evacuation system. Also bathroom door handle to be changed to lever.
|
BLD-Final | 8/10/2015 | 8/11/2015 | 8/11/2015 | P | CANC |
Mike Jordan
|
|
|
Please call for access
Thanks Phone #: ###-#### >> Inspection requested via web by matthew greenman Inspection cancelled from web by: matthew greenman
|
BLD-Framing/Rough-in | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Mike Jordan
|
|
|
Please call for access thanks Phone #: ###-#### Inspection requested via web by matthew greenman
|
BLD-Framing/Rough-in | 7/8/2015 | 7/9/2015 | 7/9/2015 | A | NR |
Mike Jordan
|
|
|
Please call prior for access thanks Phone #: ###-#### Inspection requested via web by matthew greenman. Needs electrical rough in forst.
|