Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberBLD15-01189
StatusFinaled
Name HC COMPANY INC
Site Address 365 N WHITEWATER PARK BLVD
Project NameWhitewater Clubhouse Remodel
Customer Number 
ePlanReviewYes
Description
(WHITEWATER CLUBHOUSE REMODEL AND ADDITION) This building does not have a fire sprinkler system. To remodel and construct additions to an existing clubhouse that serves an existing apartment complex. To construct a 392 square foot 1st story infill addition, two new canopies (473 sq. ft. and 399 sq. ft.), and a new 1,363 square foot 2nd story addition within the existing gym. After the work is completed, this building will have a total floor area of about 11,239 square feet (9,876 square foot 1st story and 1,363 square foot 2nd story). Work is to include sheet steel roof coverings, rough-sawn cedar barn siding, hardboard board and batten siding and trims, two interior stairways, interior nonbearing walls, a double sided gas fireplace in an exterior wall, millwork, and finishes. Structural work includes concrete footings, concrete piers, concrete stem walls, wood beams, wood shear walls, hold downs, steel columns, steel beams, wood floor diaphragm with TJI floor joists, wood bearing walls, and engineered wood scissor trusses. Special Inspection is required for concrete, welding, bolting, and epoxy anchors. The truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/20/201511/20/201511/20/2015PPASS
DetailsTony Young
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
FIRE-Final Inspection11/19/201511/19/201511/19/2015PPASS
DetailsJim Page
No fire sprinklers associated with this project, no fire alarms associated with this project. Life fire safety inspection passed/complete.
BLD-Energy code compliance9/23/20159/24/20159/24/2015APASS
DetailsJim Sly
Jody Phone #: ###-####
BLD-Framing/Rough-in9/15/20159/15/20159/15/2015APART
DetailsPhil Shearer
Review stairs and handrail oprions. Please call Nic half an hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen. Interior nonbearing walls
BLD-Framing/Rough-in9/11/20159/11/20159/11/2015PPART
DetailsJim Storey
Framing Inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen interior sheer nailling ok/ stair rise and run not corect/
BLD-Framing/Rough-in9/2/20159/2/20159/3/2015PPASS
DetailsDave Hannah
Shear wall inspection in gym. Please call Nic half hour before inspection. Prefer late pm if possible. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen
BLD-Footing8/5/20158/5/20158/6/2015PPART
DetailsDave Hannah
Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic van Diepen ok after mti spec inspection sign off
BLD-Footing7/23/20157/24/20157/24/2015PPEND
DetailsDave Hannah
rebar, 2:00PM pour time; Chris Phone #: ###-#### ok after spec inspection signs off