Permit Information
Permit NumberBLD15-01213
StatusFinaled
Name SUMMIT DEVELOPMENT INC
Site Address 12063 W OVERLAND RD
Project NameCantabria Carport
Customer Number 
ePlanReviewYes
Description
(CANTABRIA APARTMENTS - (22)4 Stall Carport) Permit is to install 22 new 4 stall steel framed carports on one parcel of land per the approved plans and the attached engineering. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/9/20162/9/20162/9/2016PPASS
DetailsMike Jordan
DOC - Permit Finaled2/9/20162/9/20162/9/2016PPASS
DetailsMike Jordan
FIRE-Final Inspection2/9/20162/9/20162/9/2016PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final2/8/20162/9/20162/9/2016ACANC
DetailsMike Jordan
Please call ahead for access, Dave has plans in hand - Dave Phone #: ###-####. Moved to pm.
FIRE-Final Inspection2/5/20162/8/20162/8/2016ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Tyler Hildebrand Inspection cancelled from web by: Tyler Hildebrand
BLD-Final2/5/20162/8/20162/8/2016ACANC
DetailsMike Jordan
Carport Final Phone #: ###-#### >> Inspection requested via web by Tyler Hildebrand Inspection cancelled from web by: Tyler Hildebrand
BLD-Wall Bracing12/10/201512/11/201512/11/2015APASS
DetailsJim Sly
Dave Phone #: ###-####
Last 4 holes ......OK See previous inspection comments.
BLD-Foundation12/9/201512/9/201512/9/2015PPART
DetailsMike Jordan
Rebar // Dave Phone #: ###-####. No plans or new engineering on site. Per Bob Archibald, allowed concrete to be placed, but engineering will be required prior to final inspection. Footings were approx. 4ft.x4ft. 34inches to 42 inches deep with two mats of 4#5 rebar each way.
BLD-Foundation12/3/201512/4/201512/4/2015APART
DetailsMike Jordan
rebar; Dave Phone #: ###-####. No plans or new engineering on site. Per Bob Archibald, allowed concrete to be placed, but engineering will be required prior to final inspection. Footings were approx. 4ft.x4ft. 34inches to 42 inches deep with two mats of 4#5 rebar each way.
BLD-Foundation11/24/201511/25/201511/25/2015AFAIL
DetailsMike Jordan
Rebar // Dave Phone #: ###-####. Holes not ready, will need to submit new engineering to city for approval for change in supplier.
BLD-Footing7/28/20157/28/20157/28/2015PPASS
DetailsMike Jordan
Ken Phone #: ###-####
BLD-Footing7/23/20157/24/20157/24/2015APASS
DetailsMike Jordan
Jim Phone #: ###-####