BLD-Final | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | PASS |
Dave Hannah
|
|
|
James Phone #: ###-#### ok for perm occ
|
BLD-Final | 12/8/2015 | 12/8/2015 | 12/8/2015 | P | PART |
Mike Jordan
|
|
|
Temp only - James Phone #: ###-####. Ok for temp occ. Self service counters more than the 34 inch max height allowed, restroom mirrors bottom edge greater than 40 inches max allowable height. Contractor to provide documentation showing that locking hardware is ADA compliant on restroom doors.
|
BLD-Final | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-####. Needs zoning final.
|
FIRE-Final Inspection | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 12/3/2015 | 12/4/2015 | 12/4/2015 | P | FAIL |
Troy Cobbley
|
|
|
The sign and door lock are done but the duct smoke detectors will not be ready until Monday
|
FIRE-Final Inspection | 12/3/2015 | 12/3/2015 | 12/3/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire access signage as discussed, remove the deadbolt at door 113, provide modifications to the duct smoke detectors as discussed and test.
|
BLD-Ceiling Grid Inspection | 11/24/2015 | 11/25/2015 | 11/25/2015 | P | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####
|
FIRE-Final Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved notes, provide address, provide all doors/hardware, install and provide testing of all exit signs and emergency lights, provide testing of the duct smoke detectors (incorrect remote annunciators have been provided), provide approval from plan review for keyed deadbolt at door 113.
|
BLD-Ceiling Grid Inspection | 11/17/2015 | 11/18/2015 | 11/18/2015 | P | PART |
Jim Sly
|
|
|
James Phone #: ###-#### Front 1/2f
|
BLD-Ceiling Grid Inspection | 11/9/2015 | 11/9/2015 | 11/9/2015 | P | PASS |
Mike Jordan
|
|
|
would like call ahead; James Phone #: ###-####. Grid in play area only ok.
|
BLD-Framing/Rough-in | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####. Exterior canopies ok.
|
BLD-Energy code compliance | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####
|
BLD-Energy code compliance | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PART |
Mike Jordan
|
|
|
Needs to complete insulation at electrical room wall and complete foam seal on top plates for fireblock.
|
BLD-Energy code compliance | 10/12/2015 | 10/13/2015 | 10/13/2015 | A | NR |
Mike Jordan
|
|
|
James Phone #: ###-####. MOved to pm.
|
BLD-Energy code compliance | 10/8/2015 | 10/12/2015 | 10/12/2015 | A | PART |
Mike Jordan
|
|
|
James Phone #: ###-####. Airseal only.
|
BLD-Framing/Rough-in | 10/8/2015 | 10/8/2015 | 10/8/2015 | P | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####
|
BLD-Wall Bracing | 9/17/2015 | 9/17/2015 | 9/17/2015 | P | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####. Exterior shear ok.
|
BLD-Wall Bracing | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | FAIL |
Mike Jordan
|
|
|
James Phone #: ###-####
|
BLD-Other | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | DEFR |
Mike Jordan
|
|
|
rebar; James Phone #: ###-####. special inspector on site.
|
BLD-Concrete | 6/29/2015 | 6/30/2015 | 6/30/2015 | A | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####. perimeter footings ok.
|