FIRE-Final Inspection | 10/8/2015 | 10/8/2015 | 10/8/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 10/5/2015 | 10/6/2015 | 10/6/2015 | A | PART |
Troy Cobbley
|
|
|
A temporary for fire life safety is being given until the possibly related vanilla finsh with Sundance Construction has been finaled or verified that it is not associated with this project.
|
BLD-Final | 10/5/2015 | 10/6/2015 | 10/5/2015 | A | DONE |
Jim Storey
|
|
|
Carry Phone #: ###-####
|
BLD-Final | 10/2/2015 | 10/5/2015 | 10/5/2015 | A | PASS |
Jim Storey
|
|
|
would like call ahead; Cari Phone #: ###-####final ok pending fire
|
FIRE-Final Inspection | 10/2/2015 | 10/5/2015 | 10/5/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need insulation attached in more locations in Mech Room 125, exit signs and emergency lights still did not get repaired and there is still the possible issue with the vanilla finish permit
|
FIRE-Final Inspection | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide correct address, repair exit signs and emergency lights, repair insulation in Mech Room 125, provide inspection for the open vanilla finish permit (Sundance Const.), and provide verification of annual inspections for fire sprinkler and fire alarm systems.
|