Permit Information
Permit NumberBLD15-01780
StatusFinaled
Name MARK GUHO CONSTRUCTION COMPANY
Site Address 11500 W FAIRVIEW AVE
Project NameTates Rents
Customer Number 
ePlanReviewYes
Description
(TATES RENTS) To demolish portions of the building including an existing greenhouse, remodeling an existing 4,815 sq. ft. building for an equipment rental facility per approved plans. Scope will include site work, a propane filling station, complete interior remodel of existing building and the construction of a separate 1,672 sq. ft. wash bay/covered storage structure on the site. The occupancy certificate for this project includes all three building on the site as they comply as a single building for height and area. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/18/20164/18/20164/18/2016PDONE
DetailsJim Sly
Ok per Jim Sly
FIRE-Final Inspection4/4/20164/4/20164/4/2016PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Final3/23/20163/24/20163/24/2016PCANC
DetailsJim Sly
Bill Phone #: ###-####
BLD-Final3/23/20163/25/20163/24/2016APART
DetailsJim Sly
Bill Phone #: ###-####
OK for Temp. Occ. OK for Perm Occ when Fire perms.
BLD-Final3/22/20163/23/20163/23/2016PNR
DetailsJim Sly
Bill Phone #: ###-####
Need Zoning Note.....Fire Temp.
FIRE-Final Inspection3/22/20163/23/20163/23/2016APART
DetailsTroy Cobbley
A temporary occupancy is being given with Romeo's permission until the LP dispencer has been reviewed/approved by the Fire Dept. All other corrections have been addressed.
BLD-Final3/15/20163/16/20163/16/2016PCANC
DetailsJim Sly
Phone #: ###-#### Inspection cancelled from web by: Letitia Gallop // did not want to reschedule at this time
FIRE-Final Inspection3/15/20163/16/20163/16/2016AFAIL
DetailsTroy Cobbley
Need single action hardware on the west and the east facing double doors (door schedule was unavailable), need address numbers, need fencing/gates installed, need pavement installed, need operational permits from fire dept., need signage at the fill station. See the redlines on the fire dept plan review comments for all corrections needed.
BLD-Framing/Rough-in2/10/20162/11/20162/11/2016APART
DetailsJim Sly
Bill Phone #: ###-####
Framing on wash bay and canopy on wash bay....OK
BLD-Energy code compliance12/22/201512/22/201512/22/2015PPASS
DetailsJim Sly
Nate Phone #: ###-####
BLD-Framing/Rough-in12/18/201512/21/201512/21/2015APASS
DetailsJim Sly
nate Phone #: ###-####
FIRE-Conference10/19/201510/19/201510/19/2015PDONE
DetailsTroy Cobbley
Discussed bollard placement with Nate. The bollards at either end are spaced too far apart and all of the bollards, per Nate, will be less than 3'-0" to the equipment which does not meet IFC 312
BLD-Foundation10/7/201510/8/201510/8/2015APASS
DetailsJim Sly
Nate Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Footing10/2/201510/5/201510/5/2015PPASS
DetailsJim Storey
Austin Phone #: ###-#### pending si report