Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberBLD15-01869
StatusFinaled
Name LAYTON CONSTRUCTION
Site Address 11196 W FAIRVIEW AVE
Project NameLarry H. Miller Boise Subaru
Customer Number 
ePlanReviewYes
Description
(Larry H. Miller Boise Subaru) Permit to construct a new 39,000 square foot two story automobile dealership. The second floor is 2,098 square feet. This building is fire sprinklered with a NFPA 13 system for Unlimited Area Building provisions (Section 507.4 / 2012 IBC). Work to include: new foundation, new exterior walls, new roof construction, new interior walls to define spaces as noted on approved plans, new electrical, new mechanical, new plumbing, new interior finishes, new equipment, and related site improvments. This building is required to be fully fire spinklered in accordance with NFPA 13 and alarmed in accordance with NFPA 72. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/28/20188/29/20188/29/2018APASS
DetailsJim Sly
Quinton Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection8/28/20188/28/20188/28/2018PPASS
DetailsTroy Cobbley
Life safety passed. FIre pump and building expansion covered under new permits


Quentin Phone #: ###-####
BLD-Final12/1/201712/1/201712/3/2017PPEND
DetailsJim Sly
See Fire.........
BLD-Aging Inspection9/6/20179/6/20179/14/2017 CANC
DetailsJim Sly
BLD-Aging Inspection5/9/20175/9/20175/9/2017 CANC
DetailsJim Sly
FIRE-Conference8/15/20168/15/20168/15/2016PDONE
DetailsTroy Cobbley
Per Assistant Chief Ron Johnson the Temporary Occupancy is to continue until directed otherwise. Included is the email dated 8/15/16 giving current status.



From: Ronald Johnson
Sent: Monday, August 15, 2016 10:04 AM
To: Quinton Boyer
Cc: Tom Easton ; Randy Bowron ; Mike Bierman ; Tim Frost ; Scott Arellano ; Romeo Gervais
Subject: Fire Flow for Larry Miller Subaru



Mr. Boyer,



I met Suez Water field techs last week to witness a flow test at the fire hydrant at the northwest corner of Larry Miller Subaru. The results of the flow test are as follows.



Outlet: 4.5”, Discharge Coefficient .9

Static: 57

Pitot: 26

Residual: 45

Actual Flow: 2772 gpm

Flow at 20psi: 5092 gpm



The available fire flow as calculated using the flow test does not support a properly functioning fire sprinkler system as designed. I discussed these results with Suez and inquired if there would be any stability increase in the system in the near future. There are no plans for any improvements that would stabilize or increase the pressure in this area in the foreseeable future. Unfortunately, the sprinkler system for Larry Miller Subaru was designed using a fire flow that does not reflect the significant daily drop in pressure. This daily drop in pressure lasts several hours and is expected to occur at least 3.5 to 4 months of the year. If a fire were to occur in the building, the sprinkler system may not be sufficient to keep it in check or extinguish the fire during several hours of the day. I know this is very inconvenient and will likely be expensive to resolve, so I am open to a reasonable timeline for repairs. Please respond with a plan and proposed timeline. I am willing to discuss this and answer questions you and the owner may have by phone or in person. Would you mind forwarding owner contact information to me so I can contact them?



Regards,




cid:image001.jpg@01CE20C9.F3E72450

Ron Johnson

Division Chief – Assistant Fire Marshal

FIRE-Conference7/8/20167/8/20167/8/2016ADONE
DetailsTroy Cobbley
60 psi on the guage this morning
FIRE-Conference7/6/20167/7/20167/7/2016ADONE
DetailsTroy Cobbley
Pressure was 64psi this morning
FIRE-Conference7/6/20167/6/20167/6/2016ADONE
DetailsTroy Cobbley
Pressure was 62psi this morning
FIRE-Conference7/5/20167/5/20167/5/2016ADONE
DetailsTroy Cobbley
Reading on the guage this morning was 70psi
FIRE-Conference7/1/20167/1/20167/1/2016ADONE
DetailsTroy Cobbley
57psi on the guage this morning
FIRE-Conference6/30/20166/30/20166/30/2016ADONE
DetailsTroy Cobbley
Pressure this morning was 69psi
FIRE-Conference6/29/20166/29/20166/29/2016ADONE
DetailsTroy Cobbley
57psi on the guage at 7:00 am this morning
FIRE-Conference6/28/20166/28/20166/28/2016ADONE
DetailsTroy Cobbley
I witnessed 64psi at the base of riser.
FIRE-Conference6/28/20166/28/20166/28/2016ADONE
DetailsTroy Cobbley
This inspection actually occured on 6/27/16 where I witnessed pressure at the base of riser at 59psi
BLD-Final6/8/20166/8/20166/8/2016PPART
DetailsJim Sly
Quinton Phone #: ###-####
OK For Temp. Occ. OK for Perm Occ. when ACHD, Electrical, Mechanical, and the Three fire inspections are finaled.
BLD-Final6/8/20166/8/20166/8/2016APART
DetailsTroy Cobbley
Per the Fire Marshal, a TCO can be issued for the building permit (BLD15-01869) for the next 30 days. The static pressure at the base of the fire riser will need to be monitored and recorded over the next 30 days by the general contractor. These readings will be evaluated by the Fire Marshal at the end of the 30 days to determine if fire sprinkler system design changes will be necessary under (FIR15-00822) to accommodate the actual water supply available onsite.
BLD-Final6/2/20166/3/20166/3/2016ANR
DetailsJim Sly
Temp Final - Quinton Phone #: ###-####
FIRE-Final Inspection6/2/20166/3/20166/3/2016APART
DetailsTroy Cobbley
Temp 30 day Final - Quinton Phone #: ###-####
FIRE-Final Inspection6/1/20166/2/20166/2/2016AFAIL
DetailsTroy Cobbley
Need the project related fire sprinkler permit finaled prior to a life safety final being given. All other life safety items have been addressed.
BLD-Final6/1/20166/2/20166/2/2016PCANC
DetailsJim Sly
Layton Phone #: ###-####
FIRE-Conference5/26/20165/26/20165/26/2016PDONE
DetailsTroy Cobbley
For a final sign off the project related fire alarm and fire sprinkler permits need addressed. Fire alarm plans need resubmitted and notification tested. Fire sprinkler forward flow is only proving half of the required water for the system. For life safety the signage needs to be provided as discussed for the Oil Storage room.
BLD-Final5/25/20165/26/20165/26/2016PCANC
DetailsJim Sly
Cancele per Clayton Phone #: ###-####
FIRE-Final Inspection5/25/20165/25/20165/25/2016PFAIL
DetailsTroy Cobbley
Todays inspection I verified that the exit signs and emergency lights have been repaired/completed
FIRE-Final Inspection5/20/20165/24/20165/24/2016PCANC
DetailsTroy Cobbley
Clinton Phone #: ###-####
FIRE-Conference5/23/20165/23/20165/23/2016PDONE
DetailsTroy Cobbley
I performed a life safety inspection. I noted exit signs and emergency lights that are non functional, not all fire extinguishers are mounted and not all of the door hardware is installed. Emergency lights are missing at the east end of the show room, three thumbturn dead bolts need to be removed from office doors, address numbers on three sides of the building need installed, signage at facp/riser and electrical rooms needs installed.
FIRE-Conference4/29/20165/11/20165/11/2016ADONE
DetailsTroy Cobbley
Quinon and I went over general life safety requirements
FIRE-Conference4/29/20164/29/20164/29/2016PDONE
DetailsTroy Cobbley
The project superintendant and I spoke about general life safety requirements and he provided documentation that the wood sheating that had been installed above the showroom windows was fire treated.
BLD-Ceiling Grid Inspection4/28/20164/29/20164/29/2016APASS
DetailsJim Sly
CLINTON Phone #: ###-####
BLD-Energy code compliance3/17/20163/18/20163/18/2016APASS
DetailsJim Sly
Insulation // Clinton Phone #: ###-####
BLD-Framing/Rough-in3/17/20163/18/20163/18/2016APASS
DetailsJim Sly
Clinton Phone #: ###-####
BLD-Framing/Rough-in3/14/20163/15/20163/15/2016APART
DetailsJim Sly
Interior only, showroom - Quinton Phone #: ###-####
Everything except restrooms ......OK.
BLD-Framing/Rough-in2/29/20162/29/20162/29/2016PPART
DetailsJim Sly
Quiton-partial-exterior farming on radius wall Phone #: ###-####
Front radius soffit .....OK.
BLD-Foundation2/9/20162/9/20162/9/2016PPART
DetailsJim Sly
Quintin Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Concrete2/9/20162/9/20162/9/2016PPART
DetailsJim Sly
service area; Quintin Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Other12/1/201512/3/201512/3/2015PPART
DetailsJim Sly
masonary grout pour (12ft lift on east side, 16ft lift west side), reinforced slab (showroom side slab area C ) - Clinton Phone #: ###-####
OK pending MTI specvial insp, tests and approvals.
BLD-Foundation11/23/201511/25/201511/25/2015APEND
DetailsDave Hannah
concrete pour, showroom ; Quintin Phone #: ###-####
BLD-Foundation11/23/201511/24/201511/24/2015PPART
DetailsJim Sly
grout, service side - 12'' tall lift ; Quintin Phone #: ###-####
MTI on site.
DOC - Permit Finaled11/24/201511/24/201511/24/2015PPASS
DetailsJim Sly
BLD-Foundation11/23/201511/23/201511/23/2015PPART
DetailsJim Sly
grout, service side - 8'' tall lift ; Quintin Phone #: ###-####
MTI on site.
BLD-Foundation11/19/201511/20/201511/20/2015APART
DetailsJim Sly
rebar; Quintin Phone #: ###-####
MTI on site.
BLD-Concrete11/2/201511/3/201511/4/2015PPART
DetailsJim Sly
showroom side, Grout, 2pm pour; Quintin Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Footing10/28/201510/29/201510/29/2015APASS
DetailsJim Sly
exterior footing for showroom side (south side)Pouring at 3 - Quinton Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Foundation10/27/201510/27/201510/27/2015PPART
DetailsMike Jordan
Quinten-as late as possible wants to pour at 7:00 AM tomorrow-interior footing on north side of the project Phone #: ###-####. INterior footings for service bay area. Work in progress, pending special inspection.
BLD-Foundation10/26/201510/26/201510/26/2015PPART
DetailsJim Sly
Quinten Phone #: ###-####
Grid line 3 and Int pads North of. OK pending MTI special inspections, tests and approvals.
BLD-Conference10/9/201510/9/201510/9/2015PDONE
DetailsJim Sly
Please call ahead to meet - Clinton Phone #: ###-####