BLD-Final | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | PASS |
Mike Jordan
|
|
|
Late PM Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | PART |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Ok for temp occ. Vertical grab bars mmounted incorrectly.
|
BLD-Final | 8/23/2016 | 8/23/2016 | 8/23/2016 | P | FAIL |
Phil Shearer
|
|
|
Kent// please call before Phone #: ###-####. Missing fire door at kitchen, ADA grab bars in restrooms.
|
FIRE-Final Inspection | 8/23/2016 | 8/23/2016 | 8/23/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled for 23AUG2016 to coincide with FIR sprinkler permit final inspection.
|
BLD-Other | 6/2/2016 | 6/6/2016 | 6/6/2016 | A | PASS |
Mike Jordan
|
|
|
would like call ahead; Brian Phone #: ###-####. base layer of 5/8 type x rock for roof/ceiling assembly ok.
|
BLD-Framing/Rough-in | 6/2/2016 | 6/2/2016 | 6/2/2016 | P | PASS |
Mike Jordan
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Mike Jordan
|
|
|
would like call ahead; Kent Phone #: ###-####. Ok to sheet rock the public side only.
|
BLD-Energy code compliance | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PEND |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Energy code ok. Pending resolution of mech. issues.
|
BLD-Conference | 4/18/2016 | 4/18/2016 | 4/18/2016 | A | DONE |
Mike Jordan
|
|
|
Went over Roof ceiling assembly with contractor.
|
BLD-Framing/Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PASS |
Mike Jordan
|
|
|
Kent-early if possible Phone #: ###-####. All framing issues have been resolved. Ok to insulate. Advise Kent to reschedule mech. rough in inspection and noted to him the correction notice from mech. to resubmit plans.
|
BLD-Conference | 4/7/2016 | 4/7/2016 | 4/7/2016 | P | PEND |
Bill VanDegrift
|
|
|
needed contact number to tell contractor I left a correction notice for dampers.
|
BLD-Framing/Rough-in | 4/6/2016 | 4/7/2016 | 4/7/2016 | P | PART |
Mike Jordan
|
|
|
would like call ahead; Kent Phone #: ###-####. Transfer showers have been replaced and our now compliant. Anchor bolts installed on interior bearing walls. Fire dampers still need to be installed on resident/living side and plate washers on exterior shear walls.
|
BLD-Framing/Rough-in | 3/2/2016 | 3/3/2016 | 3/3/2016 | A | PART |
Mike Jordan
|
|
|
would like call 30min ahead; Kent Phone #: ###-####. . ok to insulate interior walls. Transfer shower issue not yet resolved. Provide fix from enginner of record on miising anchor bolts and interior bearing walls. BAthroom vent fans in residence require fire dampers. All other issues have been resolved.
|
BLD-Conference | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 2/5/2016 | 2/5/2016 | 2/5/2016 | P | FAIL |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Provide truss enginering for framing inspection. Providte the required48 inch clearance on transfer shower from control wall. Provide membrane penetration protection on can lights. Provide additional details on how to provide continous 1hr. protection on ceiling at archway. All penetrating items through the double top plates shall be protected with an approved 1hr. listed fire stop. Correction notice posted.
|
BLD-Framing/Rough-in | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | NR |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Needs sprinkler rough in inspection.
|
BLD-Wall Bracing | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Exterior shear walls only ok.
|
BLD-Conference | 11/10/2015 | 11/12/2015 | 11/12/2015 | A | PART |
Mike Jordan
|
|
|
Ken Phone #: ###-####. Ok to set windows. No approved plans on site. contractor to recall inspection.
|
BLD-Footing | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Energy code compliance | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Mike Jordan
|
|
|
Insultaion // Rob Phone #: ###-####. Rigid insulation ok. Contacted rob to let him know that there is vegetation on interior portion of pad that will need to bo removed prior to backfilling.
|
BLD-Foundation | 9/21/2015 | 9/22/2015 | 9/22/2015 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 9/18/2015 | 9/21/2015 | 9/21/2015 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Conference | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | DONE |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|