BLD-Aging Inspection | 7/3/2017 | 7/3/2017 | 7/10/2017 | | PASS |
Jim Storey
|
|
|
Jason Blais ok's a 60 day extension grood from 5/31/17
|
BLD-Aging Inspection | 5/1/2017 | 5/1/2017 | 5/1/2017 | | PASS |
Jim Storey
|
|
|
Jason Blais ok's a 60 day extension grood from 5/31/17
|
FIRE-Final Inspection | 2/27/2017 | 2/27/2017 | 2/27/2017 | A | PASS |
Jim Page
|
|
|
Racking permit inspection complete, final for life fire safety passed/complete
|
BLD-Final | 2/23/2017 | 2/23/2017 | 2/23/2017 | A | PASS |
Jim Storey
|
|
|
This inspection is for a T-CO. Sign off card is on counter of sales area. Phone #: ###-#### Inspection requested via web by Arn Kniffen pending pw and p&z and mech temp.
|
FIRE-Final Inspection | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PART |
Jim Page
|
|
|
Partial life fire safety inspection complete. Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is in place. There is a building permit for racking associated with this tenant that is not attached to this project (BLD17-00043), this permit is in issued status, the racking permit will need a final inspection performed, when the racking permit inspection is complete and passed BLD15-01997 permit can be finaled for fire life safety. Signage for the FACP room as well as signage for fire sprinkler riser access will be installed, will verify installation of signage during racking permit inspection
|
BLD-Ceiling Grid Inspection | 1/12/2017 | 1/13/2017 | 1/13/2017 | A | PASS |
Jim Storey
|
|
|
arn Phone #: ###-####
|
BLD-Framing/Rough-in | 12/29/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Jim Storey
|
|
|
arn Phone #: ###-#### ceilling ok pending others
|
BLD-Energy code compliance | 11/18/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Jim Storey
|
|
|
Arn Phone #: ###-#### insulation ok to cover all walls
|
BLD-Framing/Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PASS |
Jim Storey
|
|
|
Arn Phone #: ###-#### framing a insulation
|
BLD-Framing/Rough-in | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Phil Shearer
|
|
|
Arn-ada in bathrooms Phone #: ###-####
|
BLD-Energy code compliance | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Phil Shearer
|
|
|
Arn Phone #: ###-####
|
BLD-Energy code compliance | 11/4/2016 | 11/7/2016 | 11/7/2016 | A | PASS |
Jim Storey
|
|
|
Arn Phone #: ###-#### office exterior walls ok
|
BLD-Framing/Rough-in | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | PART |
Jim Storey
|
|
|
Part // Arn Phone #: ###-#### office ok one side pending backing ada
|
BLD-Energy code compliance | 9/22/2016 | 9/22/2016 | 9/22/2016 | A | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 3852260488 >> Inspection requested via mobile web by Arn Kniffen foam insulation at grade ok to cover exterior permiter of building
|
BLD-Conference | 9/22/2016 | 9/22/2016 | 9/22/2016 | A | CANC |
Jim Storey
|
|
|
>> Inspection requested via mobile web by Arn Kniffen Inspection cancelled via mobile web on Thursday, September 22, 2016.
|
BLD-Footing | 9/16/2016 | 9/16/2016 | 9/16/2016 | A | PASS |
Jim Storey
|
|
|
ft at loading dock pass with si pending
|
BLD-Footing | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Jim Storey
|
|
|
Ron Phone #: ###-#### ft ok
|
BLD-Concrete | 8/10/2016 | 8/10/2016 | 8/10/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 6/29/2016 | 6/30/2016 | 6/30/2016 | A | PASS |
Jim Storey
|
|
|
Arn-partial inspection-grid C & 8 spot footings thru shop ingrid C-pour time 11:00 Phone #: ###-#### si mti
|