BLD-Ceiling Grid Inspection | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Matt Ferguson
|
BLD-Energy code compliance | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | PASS |
Jim Sly
|
|
|
The warehouse portion of the building needs ceiling insulation inspection. I left a letter from the architect for documentation in regards for doing blown-in in lieu of foam and batt at the roof sheathing. Phone #: ###-#### Inspection requested via web by Matt Ferguson
|
BLD-Energy code compliance | 2/26/2016 | 2/29/2016 | 2/29/2016 | A | PART |
Jim Sly
|
|
|
Matt Phone #: ###-#### West third of bldg.
|
BLD-Framing/Rough-in | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Jim Sly
|
|
|
Matt ###-####
|
BLD-Framing/Rough-in | 2/19/2016 | 2/22/2016 | 2/22/2016 | A | CANC |
Jim Sly
|
|
|
Jim- Phone #: ###-#### Inspection requested via web by Matt Ferguson
|
BLD-Foundation | 1/11/2016 | 1/12/2016 | 1/12/2016 | P | PART |
Jim Sly
|
|
|
Matt-grout Phone #: ###-#### CMU wall.......OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 12/2/2015 | 12/3/2015 | 12/3/2015 | P | PART |
Jim Sly
|
|
|
mono-footing; Matt Phone #: ###-#### MTI on site
|
BLD-Foundation | 11/10/2015 | 11/12/2015 | 11/12/2015 | A | PART |
Jim Sly
|
|
|
Rebar // Matt Phone #: ###-#### Perimeter walls appear OK......MTI already inspected......OK pending MTI tests and approvals.
|
BLD-Conference | 11/6/2015 | 11/6/2015 | 11/6/2015 | P | PART |
Jim Sly
|
|
|
would like call ahead; Matt Phone #: ###-#### Footing OK pending soils test, Mti special inspections, tsts and approvals. Excludes interior footing.
|