BLD-Final | 12/31/2015 | 12/31/2015 | 12/31/2015 | A | PASS |
Phil Shearer
|
|
|
We installed the hardware that Troy explained to us. Bathroom signs are on. 2 Tagged fire extinguishers are there too.
Troy said he will check it out around 8am.
Thats all we needed to do. If you have any issues let me know.
The Dentist needs to have the occupancy permit today. That way he can legally treat at least one person and have project as a 2015 tax write off. Talk about Last minute!!! Thanks for your help!
Sincerely, Mike Hincy ###-#### Phone #: ###-#### Inspection requested via web by Michael Hincy
|
FIRE-Final Inspection | 12/31/2015 | 12/31/2015 | 12/31/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 12/29/2015 | 12/30/2015 | 12/30/2015 | P | NR |
Phil Shearer
|
|
|
Mike Phone #: ###-####-call for access
|
BLD-Framing/Rough-in | 12/29/2015 | 12/30/2015 | 12/30/2015 | A | PASS |
Phil Shearer
|
|
|
Mike Phone #: ###-####-call for access
|
FIRE-Final Inspection | 12/29/2015 | 12/30/2015 | 12/30/2015 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for corrections marked in red. They include door hardware and fire extinguishers.
|
BLD-Aging Inspection | 12/30/2015 | 12/30/2015 | 12/30/2015 | | CANC |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 12/29/2015 | 12/29/2015 | 12/30/2015 | | CANC |
Mike Jordan
|
|
|
|
FIRE-Conference | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the contractor and to the architect about the possible need for resumbittals of the building plans since they do not show the gas room. I suggested that they contact both building and fire review personell. I went over IFC chapter 53 requirements with the job superintendant. I was at the project due to a FIR permit for the single sprinkler head in the gas closet.
|
BLD-Framing/Rough-in | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | PART |
Mike Jordan
|
|
|
We have meet all reqirements for the structural framing. Also need to double check the ada requirements. thx Randy the project manager is there all day, his # is ###-#### Phone #: ###-#### Inspection requested via web by Michael Hincy. Ok to sheet rock the beam and accomping supports only.
|
BLD-Conference | 8/3/2015 | 8/3/2015 | 8/3/2015 | P | NR |
Dave Hannah
|
|
|
The structural engineer (feel free to call him, shawn ###-####) says that it is all there in the plans. We are on site to review with you.
Phone #: ###-#### Inspection requested via web by Michael Hincy
|
BLD-Conference | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | NR |
Mike Jordan
|
|
|
My project manager Randy will be there from noon on. we have done the demo and the framing and have a few questions about framing and ada bathroom requirements. please call if possible with an approx time. thx Phone #: ###-#### Inspection requested via web by Michael Hincy. Needs to provide the city set of approved plans and engineering for headers.
|