Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberBLD15-02243
StatusFinaled
Name INSIGHT REMODELING & PAINTING LLC
Site Address 6363 W EMERALD ST Unit: 103
Project NameBoise Family Dental
Customer Number 
ePlanReviewYes
Description
(BOISE FAMILY DENTAL) To remodel a 3,073 square foot tenant space that was last occupied by (Boise Dental Specialist) under microfiche #9613348. Work is to include: Removal of existing select nonbearing walls or doors at the accounting, X-Ray, men’s restroom and bearing wall at conference room, construction of new select bearing header walls at the conference room per attached engineering, new tempered glass and door in the conference room, new ADA compliant counter opening at the accounting office, new ADA compliant restrooms and interior finishes in compliance with Ch. 8 of the 2012 IBC. This building is not sprinklered **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/31/201512/31/201512/31/2015APASS
DetailsPhil Shearer
We installed the hardware that Troy explained to us.
Bathroom signs are on.
2 Tagged fire extinguishers are there too.

Troy said he will check it out around 8am.

Thats all we needed to do. If you have any issues let me know.

The Dentist needs to have the occupancy permit today.
That way he can legally treat at least one person and have project as a 2015 tax write off. Talk about Last minute!!!
Thanks for your help!

Sincerely, Mike Hincy ###-#### Phone #: ###-#### Inspection requested via web by Michael Hincy
FIRE-Final Inspection12/31/201512/31/201512/31/2015APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final12/29/201512/30/201512/30/2015PNR
DetailsPhil Shearer
Mike Phone #: ###-####-call for access
BLD-Framing/Rough-in12/29/201512/30/201512/30/2015APASS
DetailsPhil Shearer
Mike Phone #: ###-####-call for access
FIRE-Final Inspection12/29/201512/30/201512/30/2015AFAIL
DetailsTroy Cobbley
See the city approved plans for corrections marked in red. They include door hardware and fire extinguishers.
BLD-Aging Inspection12/30/201512/30/201512/30/2015 CANC
DetailsMike Jordan
BLD-Aging Inspection12/29/201512/29/201512/30/2015 CANC
DetailsMike Jordan
FIRE-Conference12/7/201512/7/201512/7/2015PDONE
DetailsTroy Cobbley
I spoke to the contractor and to the architect about the possible need for resumbittals of the building plans since they do not show the gas room. I suggested that they contact both building and fire review personell. I went over IFC chapter 53 requirements with the job superintendant. I was at the project due to a FIR permit for the single sprinkler head in the gas closet.
BLD-Framing/Rough-in8/17/20158/17/20158/17/2015PPART
DetailsMike Jordan
We have meet all reqirements for the structural framing. Also need to double check the ada requirements. thx
Randy the project manager is there all day, his # is ###-#### Phone #: ###-#### Inspection requested via web by Michael Hincy. Ok to sheet rock the beam and accomping supports only.
BLD-Conference8/3/20158/3/20158/3/2015PNR
DetailsDave Hannah
The structural engineer (feel free to call him, shawn ###-####) says that it is all there in the plans. We are on site to review with you.


Phone #: ###-#### Inspection requested via web by Michael Hincy
BLD-Conference7/31/20157/31/20157/31/2015PNR
DetailsMike Jordan
My project manager Randy will be there from noon on.
we have done the demo and the framing and have a few questions about framing and ada bathroom requirements.
please call if possible with an approx time. thx Phone #: ###-#### Inspection requested via web by Michael Hincy. Needs to provide the city set of approved plans and engineering for headers.