BLD-Final | 6/20/2016 | 6/21/2016 | 6/21/2016 | A | PASS |
Jim Sly
|
|
|
Rod Phone #: ###-####
|
DOC - Permit Finaled | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 4/28/2016 | 4/29/2016 | 4/29/2016 | P | PART |
Jim Sly
|
|
|
would like call ahead Phone #: ###-#### need p&z final
|
DOC - Permit Finaled | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | PART |
Jim Sly
|
|
|
All other inspections are final Phone #: ###-#### Inspection requested via web by steven barth Zoning Bonded BND 16-00031 Andrea T. OK for Temp occ.
|
FIRE-Final Inspection | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspections complete (FIR15-00793 for underground, FIR15-00865 for overhead) fire alarm inspection complete (FIR15-00902) fire alarm communicator inspection complete (FIR16-00190) Final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 3/23/2016 | 3/24/2016 | 3/24/2016 | A | CANC |
Jim Page
|
|
|
Inspection request rescheduled for 25MAR16, Steve Phone #: ###-####
|
BLD-Conference | 3/23/2016 | 3/23/2016 | 3/23/2016 | P | PEND |
Tony Young
|
|
|
Prior Final for shell Steve Barth Phone #: ###-#### Inspection requested via web by steven barth,, need trades etc.
|
BLD-Conference | 3/22/2016 | 3/23/2016 | 3/23/2016 | A | PART |
Tony Young
|
|
|
Prior Final for shell Steve Barth Phone #: ###-#### Inspection requested via web by steven barth,, walk through
|
BLD-Energy code compliance | 2/24/2016 | 2/24/2016 | 2/24/2016 | A | PASS |
Mike Jordan
|
|
|
Partial inside walls in order to remove equipment from that bay. Phone #: ###-#### Inspection requested via web by steven barth
|
BLD-Conference | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | PART |
Tony Young
|
|
|
Framing inspection Plumbing is good. Elec called to today. Mech is stub above only. Inspection for insulation. Phone #: ###-#### Inspection requested via web by steven barth,,, walls ok to insulate
|
BLD-Framing/Rough-in | 2/19/2016 | 2/19/2016 | 2/19/2016 | P | PART |
Jim Sly
|
|
|
Framing Phone #: ###-#### Inspection requested via web by steven barth Interior non bearing demising walls OK to cover..........Providing that they do not contain any utilities.
|
BLD-Conference | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PART |
Tony Young
|
|
|
Demising walls inside the building Phone #: ###-#### Inspection requested via web by steven barth,, 3 demising walls ok pending adding sill bolts within 12" of ends
|
BLD-Wall Bracing | 2/4/2016 | 2/5/2016 | 2/5/2016 | A | PASS |
Tony Young
|
|
|
Sheer inspection. Thankyou. Phone #: ###-#### Inspection requested via web by steven barth,,, exterior ok
|
BLD-Wall Bracing | 1/26/2016 | 1/27/2016 | 1/27/2016 | A | PART |
Tony Young
|
|
|
Partial sheer nail inspection for area to receive electrical switch gear,. Steven Barth contact. Phone #: ###-#### Inspection requested via web by steven barth,, ok
|
BLD-Footing | 10/14/2015 | 10/15/2015 | 10/16/2015 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by steven barth Perimeter Fooping OK pending GeoTech Special inspection, tests and approvals.
|