Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberBLD15-02399
StatusFinaled
Name HAWKINS COMPANIES LLC
Site Address 7700 W STATE ST
Project NameNorth Pointe Retail Building 2
Customer Number 
ePlanReviewYes
Description
(NORTH POINTE RETAIL / RESTURANT – BLDG #2 – Shell and Core) Permit is to construct a 7,393 square foot Retail / Office / Assembly Shell building. This building is constructed as a wood frame building and a concrete footing. Work includes: new foundation, new exterior walls, new mechanical, stubbing in plumbing into the building, site work, new wood frame exterior walls, new manufactured wood truss roof system, and new electrical (Exterior Lighting Approved). This building will be fully Fire Sprinklered with an approved Fire Alarm system. System shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. NOTE: In accordance with Section C401.2 option #1 of the 2012 IECC; ANSI/ASHREA/IESNA 90.1 were used to show compliance with the Energy Code. The lighting installed within the tenant spaces shall also comply with ASHREA. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/30/20167/1/20167/1/2016APASS
DetailsJim Sly
Rod Phone #: ###-####
DOC - Permit Finaled7/1/20167/1/20167/1/2016PPASS
DetailsJim Sly
BLD-Final4/28/20164/29/20164/29/2016PNR
DetailsJim Sly
would like call ahead Phone #: ###-####
Need Public works and Zoning final
FIRE-Final Inspection3/28/20163/28/20163/28/2016PPASS
DetailsJim Page
Fire sprinkler inspections complete (FIR15-00792 for underground, FIR15-00910 for overhead) fire alarm inspection complete (FIR15-00901) fire alarm communicator inspection complete (FIR16-00189) Final life fire safety inspection passed/complete
FIRE-Final Inspection3/24/20163/25/20163/25/2016ACANC
DetailsJim Page
Could not complete life fire safety inspection due to FIR permits still in the issued status. Reminded contractors numorous times about FIR permits needing to be finaled before life fire safety inspection can be completed. Inspection request cancelled, life fire safety will be completed after FIR permits are finaled.
FIRE-Final Inspection3/23/20163/24/20163/24/2016ACANC
DetailsJim Page
Inspection request rescheduled for 25MAR16, Steve Phone #: ###-####
BLD-Final3/23/20163/23/20163/23/2016PNR
DetailsTony Young
Wanting final for shell Phone #: ###-#### Inspection requested via web by steven barth,, need trades,, prior notes
BLD-Conference3/22/20163/23/20163/23/2016APART
DetailsTony Young
Wanting final for shell Phone #: ###-#### Inspection requested via web by steven barth,, walk through on final.. need all trades,, including ACHD, zoning,, final letter of ok from engineer?,, verify tempered glass locations
BLD-Energy code compliance1/29/20162/1/20162/1/2016APASS
DetailsJim Sly
inside insulation and vapor barrier except the lower 4 feet left open until floor area is graded. Phone #: ###-#### Inspection requested via web by steven barth
Talked to Steve.......OK to rock lower 4' after vapor barrier pulled back down and concrete floor completed.
BLD-Energy code compliance1/28/20161/29/20161/29/2016PDEFR
DetailsTony Young
inside insulation and vapor barrier except the lower 4 feet left open until floor area is graded. Phone #: ###-#### Inspection requested via web by steven barth
BLD-Framing/Rough-in1/25/20161/26/20161/26/2016APART
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by steven barth
Fire riser room has plywood on one inside wall with electrical panels attached. Arch to provide fix for maintaing 1 hr wall. OK to insulate.
BLD-Wall Bracing12/24/201512/28/201512/28/2015APASS
DetailsTony Young
AM pls. Inspection for shear wall. Phone #: ###-#### Inspection requested via web by steven barth,, exterior ok
BLD-Framing/Rough-in12/23/201512/24/201512/24/2015APART
DetailsTony Young
AM pls. Inspection for shear wall. Phone #: ###-#### Inspection requested via web by steven barth,, work in progress
BLD-Foundation11/2/201511/3/201511/3/2015PPASS
DetailsTony Young
Place concrete at 2pm. Third Party inspection by Geo Tec. Requested inspection after lunch pls. Phone #: ###-#### Inspection requested via web by steven barth,, met engineer on site,, Luke,, he is watching job
BLD-Footing10/27/201510/28/201510/28/2015APEND
DetailsDave Hannah
Special inspection performed by Geo Tec AM. Steel for footing. Pour at 11Am Phone #: ###-#### Inspection requested via web by steven barth crew about 90% spec inspection will sign off