BLD-Final | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Jim Sly
|
|
|
Rod Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2016 | 7/1/2016 | 7/1/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 4/28/2016 | 4/29/2016 | 4/29/2016 | P | NR |
Jim Sly
|
|
|
would like call ahead Phone #: ###-#### Need Public works and Zoning final
|
FIRE-Final Inspection | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspections complete (FIR15-00792 for underground, FIR15-00910 for overhead) fire alarm inspection complete (FIR15-00901) fire alarm communicator inspection complete (FIR16-00189) Final life fire safety inspection passed/complete
|
FIRE-Final Inspection | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | CANC |
Jim Page
|
|
|
Could not complete life fire safety inspection due to FIR permits still in the issued status. Reminded contractors numorous times about FIR permits needing to be finaled before life fire safety inspection can be completed. Inspection request cancelled, life fire safety will be completed after FIR permits are finaled.
|
FIRE-Final Inspection | 3/23/2016 | 3/24/2016 | 3/24/2016 | A | CANC |
Jim Page
|
|
|
Inspection request rescheduled for 25MAR16, Steve Phone #: ###-####
|
BLD-Final | 3/23/2016 | 3/23/2016 | 3/23/2016 | P | NR |
Tony Young
|
|
|
Wanting final for shell Phone #: ###-#### Inspection requested via web by steven barth,, need trades,, prior notes
|
BLD-Conference | 3/22/2016 | 3/23/2016 | 3/23/2016 | A | PART |
Tony Young
|
|
|
Wanting final for shell Phone #: ###-#### Inspection requested via web by steven barth,, walk through on final.. need all trades,, including ACHD, zoning,, final letter of ok from engineer?,, verify tempered glass locations
|
BLD-Energy code compliance | 1/29/2016 | 2/1/2016 | 2/1/2016 | A | PASS |
Jim Sly
|
|
|
inside insulation and vapor barrier except the lower 4 feet left open until floor area is graded. Phone #: ###-#### Inspection requested via web by steven barth Talked to Steve.......OK to rock lower 4' after vapor barrier pulled back down and concrete floor completed.
|
BLD-Energy code compliance | 1/28/2016 | 1/29/2016 | 1/29/2016 | P | DEFR |
Tony Young
|
|
|
inside insulation and vapor barrier except the lower 4 feet left open until floor area is graded. Phone #: ###-#### Inspection requested via web by steven barth
|
BLD-Framing/Rough-in | 1/25/2016 | 1/26/2016 | 1/26/2016 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by steven barth Fire riser room has plywood on one inside wall with electrical panels attached. Arch to provide fix for maintaing 1 hr wall. OK to insulate.
|
BLD-Wall Bracing | 12/24/2015 | 12/28/2015 | 12/28/2015 | A | PASS |
Tony Young
|
|
|
AM pls. Inspection for shear wall. Phone #: ###-#### Inspection requested via web by steven barth,, exterior ok
|
BLD-Framing/Rough-in | 12/23/2015 | 12/24/2015 | 12/24/2015 | A | PART |
Tony Young
|
|
|
AM pls. Inspection for shear wall. Phone #: ###-#### Inspection requested via web by steven barth,, work in progress
|
BLD-Foundation | 11/2/2015 | 11/3/2015 | 11/3/2015 | P | PASS |
Tony Young
|
|
|
Place concrete at 2pm. Third Party inspection by Geo Tec. Requested inspection after lunch pls. Phone #: ###-#### Inspection requested via web by steven barth,, met engineer on site,, Luke,, he is watching job
|
BLD-Footing | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | PEND |
Dave Hannah
|
|
|
Special inspection performed by Geo Tec AM. Steel for footing. Pour at 11Am Phone #: ###-#### Inspection requested via web by steven barth crew about 90% spec inspection will sign off
|