BLD-Final | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Aging Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | | PASS |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 5/20/2016 | 5/20/2016 | 5/20/2016 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Ok for temp. occ. Will be ok for perm occ. once zoning signs perm,.
|
BLD-Final | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Rescheduled for tomorrow in the pm. Needs zoning final (will be tomorrow at 10:30am)
|
FIRE-Final Inspection | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####
|
BLD-Energy code compliance | 1/22/2016 | 1/22/2016 | 1/22/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 1/21/2016 | 1/22/2016 | 1/22/2016 | A | PASS |
Mike Jordan
|
|
|
Kelly Phone #: ###-####
|
BLD-Framing/Rough-in | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | FAIL |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Patch hole sin draft stop, Firecaulk missed penetrations in draft stop. Fire caulk top of wall in upstairs mech. rooms. OK to insulate. Correction notice posted.
|
BLD-Framing/Rough-in | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Needs fire sprinkler rough in inspection.
|
BLD-Wall Bracing | 12/2/2015 | 12/3/2015 | 12/3/2015 | A | PASS |
Mike Jordan
|
|
|
Kelly Phone #: ###-####
|
BLD-Wall Bracing | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PASS |
Mike Jordan
|
|
|
Shear // Kelly Phone #: ###-####
|
BLD-Foundation | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Interior thickend footings under slab on grade.
|
BLD-Energy code compliance | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Footing | 10/15/2015 | 10/16/2015 | 10/16/2015 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Footing | 10/15/2015 | 10/15/2015 | 10/15/2015 | P | PASS |
Mike Jordan
|
|
|
Interior thickend footings.
|
BLD-Energy code compliance | 10/15/2015 | 10/15/2015 | 10/15/2015 | P | CANC |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Foundation | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 10/12/2015 | 10/13/2015 | 10/13/2015 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|