BLD-Final | 11/19/2015 | 11/20/2015 | 11/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson perm final ok pending pw sign off
|
FIRE-Final Inspection | 11/19/2015 | 11/20/2015 | 11/20/2015 | A | PASS |
Jim Page
|
|
|
FIR permit inspection for fire sprinklers complete, FIR permit inspection for fire alarms complete. Life fire safety inspection passed/complete.
|
FIRE-Alarm Testing | 11/19/2015 | 11/19/2015 | 11/19/2015 | A | CANC |
Jim Page
|
|
|
Spoke to point of contact, Scott phone number ###-####, informed him that core/shell FIR permits for alarms and fire sprinklers need to be completed before final inspection. FIR permits for fire alarms and fire sprinklers need to be complete for tenant space before final life fire safety inspection can be completed. This inspection cancelled and will be scheduled for a later date.
|
FIRE-Final Inspection | 11/19/2015 | 11/19/2015 | 11/19/2015 | A | CANC |
Jim Page
|
|
|
Spoke to point of contact, Scott phone number ###-####, informed him that core/shell FIR permits for alarms and fire sprinklers need to be completed before final inspection. FIR permits for fire alarms and fire sprinklers need to be complete for tenant space before final life fire safety inspection can be completed. This inspection cancelled and will be scheduled for a later date.
|
BLD-Conference | 11/18/2015 | 11/18/2015 | 11/18/2015 | P | DONE |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/6/2015 | 11/6/2015 | 11/6/2015 | P | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/30/2015 | 10/30/2015 | 11/2/2015 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Ceiling Grid Inspection | 11/2/2015 | 11/2/2015 | 11/2/2015 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Ceiling Grid Inspection | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 10/7/2015 | 10/8/2015 | 10/8/2015 | P | PASS |
Dave Hannah
|
|
|
This is for the restrooms and hallway hard lids and soffit framing. Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 9/30/2015 | 10/2/2015 | 10/6/2015 | P | PASS |
Dave Hannah
|
|
|
interior partial framing. Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PART |
Jim Sly
|
|
|
Scott Phone #: ###-#### Exterior pop out wall for menu board at front entry.......OK.
|