Permit Information
Permit NumberBLD15-02839
StatusFinaled
Name SAKI CONSTRUCTION LLC
Site Address 3077 N CHRISTINE ST
Project NameIslamic Center of Boise
Customer Number 
ePlanReviewYes
Description
(ISLAMIC CENTER OF BOISE) (2-1-17 PLAN MODIFICATION TO DEFER THE INSTALLATION OF A LAVATORY AND A URINAL IN THE MEN’S RESTROOM TO A LATER TIME. THE ROUGH PLUMBING TO ACCOMMODATE THOSE FUTURE FIXTURES IN THE LOCATIONS SHOWN ON THE DRAWINGS IS REQUIRED TO BE COMPATIBLE WITH THE INSTALLATION OF THOSE FIXTURES. A SHOWER IS NOT APPROVED. CJW) (7-11-16 PLAN MODIFICATION TO REMOVE EXISTING EXTERIOR OVERHEAD DOORS AND INFILL WALL OPENINGS WITH MASONRY WALLS OR FRAMED WALLS OR STOREFRONT GLAZING SYSTEMS WITH AT LEAST ONE EXTERIOR DOOR, PROVIDE A NEW DOOR OPENING IN AN EXISTING INTERIOR MASONRY WALL, CONVERT A STORAGE ROOM TO A FUTURE WARMING TYPE KITCHEN, AND COMBINE TWO (2) FORMER STORAGE ROOMS INTO ONE ROOM AND CONVERT THAT ROOM TO A SOCIAL HALL.) The fire sprinkler system is used for fire area. To convert an existing 5,933 square foot office building to a place of religious worship. After the 515 square foot canopy addition is constructed, this building will have a total floor area of about 6,448 square feet. This building will have a fire sprinkler system and a fire alarm system installed in conjunction with this permit. Work is to include interior nonbearing walls, a new exterior door with sidelights, interior doors, interior windows, and finishes. Two restrooms will be upgraded to be accessible to the disabled. The canopy addition includes concrete footings, concrete piers, steel columns, steel beams, cold formed steel trusses, structural fiber cement board roof decking, and metal roofing. Special Inspection is required for soils, concrete, welding, bolts, and post installed concrete anchors. The design for the cold formed steel trusses is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/3/20173/6/20173/6/2017PPASS
DetailsJim Sly
Adin Phone #: ###-####
OK for Perm Occ.
BLD-Final3/1/20173/2/20173/2/2017ANR
DetailsJim Sly
Adin Phone #: ###-####
FIRE-Final Inspection2/28/20173/1/20173/1/2017PPASS
DetailsTroy Cobbley
Life safety passed. Adin was going to conference with the building inspector for requirements o the one hour riser room. I noted holes in the wall and the interior doors bottom sweep catching on the carpet.
FIRE-Final Inspection2/22/20172/23/20172/23/2017AFAIL
DetailsTroy Cobbley
Provide panic hardware on the two west side doors, mount occupant load signs, provide Riser Room signage on exterior door, provide one hour riser room, provide small documents, provide 20' clearance on the south gate to the west side parking area that accesses the west side of the building.
FIRE-Conference2/23/20172/23/20172/23/2017PDONE
DetailsKatie Marron
Discussed existing gate width of 18' with Ron Johnson. He is ok with it as is since no work being completed on gate or grading and gate is not required for access to riser room. Email attached to case.
BLD-Conference1/13/20171/17/20171/17/2017ADONE
DetailsJim Sly
Adim Phone #: ###-####
BLD-Final12/9/201612/9/201612/9/2016APEND
DetailsJim Sly
Contractor to call for final insp......
BLD-Aging Inspection12/9/201612/9/201612/9/2016 CANC
DetailsJim Sly
BLD-Conference8/31/20168/31/20168/31/2016PDONE
DetailsJim Sly
Adin Phone #: ###-####
Framing OK at North wall openings.
BLD-Framing/Rough-in7/27/20167/28/20167/28/2016APART
DetailsJim Sly
Adin-front canopy Phone #: ###-####
Pull test for Special inspection on epoxy bolting for steel columns was approved .
Canopy Framing......OK.
FIRE-Conference7/27/20167/28/20167/28/2016PDONE
DetailsTroy Cobbley
Draft stops for the upright sprinklers installed piping can be covered.
BLD-Conference6/22/20166/23/20166/23/2016ADONE
DetailsJim Sly
Adin Phone #: ###-####
BLD-Framing/Rough-in5/26/20165/26/20165/26/2016PPASS
DetailsJim Sly
Adin Phone #: ###-####
BLD-Conference4/13/20164/14/20164/14/2016ADONE
DetailsJim Sly
Adin Phone #: ###-####
BLD-Foundation2/16/20162/17/20162/17/2016APART
DetailsJim Sly
Ardi Phone #: ###-####
Stairs OK.
BLD-Other1/27/20161/28/20161/28/2016ANR
DetailsJim Sly
Ardi-ramp Phone #: ###-####
BLD-Footing12/2/201512/2/201512/2/2015PNR
DetailsJim Sly
Ari Phone #: ###-####
Not ready for inspection.....Talked with Ari. Need Special insp on soils, reinforcement, epoxy and test samples. No agency notified yet.