BLD-Final | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | PASS |
Mike Jordan
|
|
|
Ready for full final now that electrical work by owners vendor has been inspected and finaled. Phone #: ###-#### Inspection requested via web by Mike Walling. ok for perm occ.
|
BLD-Final | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Walling. Ok for temp occ. Will be ok for perm. occ. once electrical signs perm.
|
FIRE-Final Inspection | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Door hardware was not installed on doors but was on site and appeared correct. It would be installed prior to the building inspection
|
BLD-Framing/Rough-in | 3/1/2016 | 3/1/2016 | 3/1/2016 | A | PASS |
Mike Jordan
|
|
|
Framing and shear wall inspection Phone #: ###-#### Inspection requested via web by Mike Walling. INterior steel stud framed walls and shear walls ok.
|
BLD-Conference | 2/10/2016 | 2/10/2016 | 2/10/2016 | A | PASS |
Mike Jordan
|
|
|
Progress inspection. Structural steel complete with special inspection. Conference on railing at ramp. Thanks. Phone #: ###-#### Inspection requested via web by Mike Walling
|
BLD-Concrete | 1/14/2016 | 1/14/2016 | 1/14/2016 | P | PART |
Mike Jordan
|
|
|
Grout for first lift at North elevation at 3:00. Thanks!! Phone #: ###-#### Inspection requested via web by Mike Walling. Work in progress. Pending special inspection.
|
BLD-Conference | 1/5/2016 | 1/6/2016 | 1/6/2016 | P | PASS |
Mike Jordan
|
|
|
Grout for 4th lift at 4:00 p.m. Phone #: ###-#### Inspection requested via web by Mike Walling. Work in progress on 12ft. to 16ft. elevation south east and west walls.
|
BLD-Other | 12/22/2015 | 12/23/2015 | 12/23/2015 | A | PASS |
Mike Jordan
|
|
|
Structural block, 4'' lift Phone #: ###-#### Inspection requested via web by Mike Walling. East, west and south walls, 0fty. to 4ft. elevation. Special inspector on site, ICC cert. verified.
|
BLD-Other | 12/22/2015 | 12/22/2015 | 12/22/2015 | P | CANC |
Mike Jordan
|
|
|
Structural block first lift at lower footing step.
Phone #: ###-#### Inspection requested via web by Mike Walling. Moved to 12-23 in the am.
|
BLD-Footing | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | PART |
Jim Sly
|
|
|
Mike Phone #: ###-#### MTI employee Brad Gehlen Certification verified ....OK Stem walls OK pending M T I special inspection, tests and approvals.
|
BLD-Foundation | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PART |
Mike Jordan
|
|
|
Tim gave ok for inspection plan mod is being done on the walls. Any questions talk with Tim W // Leonard Phone #: ###-####. Placement completed when arrived on site. Special inspector on site, need to confirm ICC cert.
|