Permit Information
Permit NumberBLD15-03329
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 611 S 8TH ST
Project NameThe Afton
Customer Number 
ePlanReviewYes
Description
(THE AFTON – PHASE I – CONCRETE PODIUM) (DRH14-00262) The fire sprinkler system (NFPA 13 below and above the podium per the “Special Design Standards for Type V Construction” ordinance) will be used for story and height increase. To construct Phase I of a multi-phase mixed use project. All other drawings are for reference only. After all phases are completed, uses are expected to include parking on the 1st and 2nd stories, live/work units on the 1st and 2nd stories, apartments on the 1st story, two story apartments on the 2nd and 3rd stories, and 1 story apartments on the 3rd, 4th , 5th, and 6th stories. Work under this permit is to include two-way post tensioned concrete slab floors with drop caps and concrete beams (where needed) supported by concrete columns and ordinary shear walls. The podium level (floor of 3rd story) will be a maximum 12 inch thick post tensioned concrete slab having a 3-hr fire-resistance-rating. The floor of the 2nd story will be an 8 inch thick post tensioned concrete slab. Special Inspection is required for soils, concrete including post tensioning, masonry, steel including welding, etc. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. This permit does not establish a Certificate of Occupancy for any portion of this building. Fire sprinkler permits and fire alarm permits are required in conjunction with future building permits. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/8/20179/8/20179/8/2017PPASS
DetailsDave Hannah
for perm occ
DOC - Permit Finaled  9/8/2017 DONE
FIRE-Final Inspection9/7/20179/7/20179/7/2017APASS
DetailsJim Page
Final life fire safety inspection passed/complete
BLD-Final8/30/20178/31/20178/31/2017ACANC
DetailsDave Hannah
Final for 201 and 202 Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Final8/21/20178/22/20178/22/2017PPART
DetailsDave Hannah
First level town homes Phone #: ###-#### Inspection requested via web by Ami Tracy ok to occ units 105,106 and 107
BLD-Framing/Rough-in6/26/20176/26/20176/26/2017PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Conference6/12/20176/12/20176/12/2017PDONE
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance5/26/20175/30/20175/30/2017APASS
DetailsDave Hannah
6th Floor Trash Chute Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance5/22/20175/23/20175/23/2017APEND
DetailsDave Hannah
1st floor - Jason Phone #: ###-####
BLD-Energy code compliance5/5/20175/5/20175/7/2017PPART
DetailsDave Hannah
6th Floor Trash Chute Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Conference4/12/20174/17/20174/17/2017APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Framing/Rough-in3/16/20173/17/20173/17/2017APEND
DetailsDave Hannah
Trash Chute Walls Phone #: ###-#### Inspection requested via web by Ami Tracy ok to cover all but for sixth floor shaft does not up though attic must cut attic trusses to get shaft though roof
BLD-Energy code compliance3/3/20173/3/20173/3/2017PNR
DetailsDave Hannah
6th Floor Rescheduled Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Wall cover2/20/20172/21/20172/21/2017APART
DetailsJim Sly
Level 6 Ceiling.....and Townhome insulation...3 units Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance2/6/20172/6/20172/6/2017PPASS
DetailsDave Hannah
6th Floor Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance2/1/20172/2/20172/2/2017ANR
DetailsDave Hannah
6th Floor Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance1/30/20171/30/20171/30/2017PPASS
DetailsDave Hannah
Insultion // Jason Phone #: ###-####
BLD-Energy code compliance1/26/20171/27/20171/27/2017APASS
DetailsDave Hannah
Unit 601 insulation - Jesse will be on site Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Energy code compliance12/30/20161/3/20171/3/2017APASS
DetailsDave Hannah
6th Floor Ceilings Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Ceiling Grid Inspection12/27/201612/28/201612/28/2016APART
DetailsDave Hannah
Phone #: ###-#### 5th floor drops ok to cover
BLD-Energy code compliance12/22/201612/22/201612/22/2016PPART
DetailsDave Hannah
Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy ok to cover 501-504
BLD-Energy code compliance12/20/201612/20/201612/20/2016PPART
DetailsDave Hannah
Insulation // Jason Phone #: ###-#### second floor two east apts ok to cover walls
BLD-Conference12/15/201612/15/201612/16/2016PPART
DetailsDave Hannah
5th Floor Framing Phone #: ###-#### Inspection requested via web by Ami Tracy second floor live work units two on th eastend ok to cover ext walls and one side int need to check floor pens and fire wall pens 4th floor west uint ok to cover all but for mec chase by front door
BLD-Wall cover12/2/201612/2/201612/2/2016ACANC
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy
BLD-Conference12/1/201612/1/201612/2/2016PPART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ami Tracy furred downs on 4th floor
BLD-Framing/Rough-in11/17/201611/18/201611/18/2016PPASS
DetailsDave Hannah
Level 1,2 & 5 - Jason Phone #: ###-####
BLD-Energy code compliance11/17/201611/18/201611/18/2016PPART
DetailsDave Hannah
Level 4 insulation - Jason Phone #: ###-#### first two units ok to cover
BLD-Framing/Rough-in11/14/201611/15/201611/15/2016APART
DetailsDave Hannah
4th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy ok to insulate
BLD-Wall Bracing11/14/201611/15/201611/15/2016APASS
DetailsDave Hannah
4th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy signed off by mti
BLD-Framing/Rough-in11/14/201611/14/201611/14/2016PDEFR
DetailsMike Jordan
4th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy. OUt of time.
BLD-Energy code compliance11/10/201611/10/201611/10/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### 3rd fl ok to cover
BLD-Energy code compliance11/8/201611/9/201611/9/2016APEND
DetailsDave Hannah
Insulation // Jason Phone #: ###-#### walls ok but need to finish fire cualking in drop ceilings
BLD-Energy code compliance11/7/201611/8/201611/8/2016APART
DetailsDave Hannah
Jason Phone #: ###-#### 3rd floor walls ok
BLD-Framing/Rough-in11/2/201611/2/201611/3/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### ok to insulate walls 3rd floor
BLD-Framing/Rough-in10/25/201610/26/201610/26/2016APEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Energy code compliance10/17/201610/17/201610/18/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### ceilings 5th floor
BLD-Energy code compliance10/12/201610/13/201610/13/2016ANR
DetailsPhil Shearer
Jason Phone #: ###-####
BLD-Energy code compliance9/21/20169/22/20169/22/2016APART
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Energy code compliance9/14/20169/15/20169/15/2016APART
DetailsDave Hannah
Unit 304 & 305 - Jason Phone #: ###-#### ceilings sheetrock also ok
BLD-Energy code compliance9/14/20169/14/20169/14/2016PDEFR
DetailsJim Storey
Unit 304 & 305 - Jason Phone #: ###-#### out of time
BLD-Energy code compliance9/8/20169/8/20169/8/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### ceilings in first 4 rooms
BLD-Framing/Rough-in9/2/20169/6/20169/6/2016APASS
DetailsDave Hannah
Roof - Jason Phone #: ###-####
BLD-Framing/Rough-in8/24/20168/24/20168/24/2016PPART
DetailsDave Hannah
Jason Phone #: ###-#### roof sheeting ok to cover
BLD-Framing/Rough-in8/15/20168/16/20168/16/2016APASS
DetailsMike Jordan
Nathan Phone #: ###-####. 1st and 2nd. floor exterior steel stud framed walls ok to cover exterior side only.
BLD-Framing/Rough-in8/3/20168/4/20168/5/2016ANR
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Framing/Rough-in8/3/20168/3/20168/3/2016PDEFR
DetailsJim Storey
Jason Phone #: ###-#### out of time rolled to am
BLD-Conference6/30/20166/30/20166/30/2016PPASS
DetailsDave Hannah
Two hour radiant // Jason Phone #: ###-####
BLD-Conference6/8/20166/9/20166/9/2016APASS
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Conference6/6/20166/7/20166/7/2016APASS
DetailsDave Hannah
Requests 9AM - Jason Phone #: ###-####
BLD-Foundation5/2/20165/2/20165/3/2016PPASS
DetailsDave Hannah
Phone #: ###-####
BLD-Framing/Rough-in3/10/20163/11/20163/14/2016APEND
DetailsDave Hannah
Jason Phone #: ###-#### frist level pt dick work in progress mti will signoff this afternoon
BLD-Other3/9/20163/9/20163/10/2016PNR
DetailsDave Hannah
Jason-post tension deck Phone #: ###-####
BLD-Foundation2/18/20162/18/20162/19/2016PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Foundation2/10/20162/10/20162/11/2016PDEFR
DetailsMike Jordan
Jason Phone #: ###-####. As per Jason foundation already placed. he noted that foundation had special inspection. Inspection was scheduled for 2-10. Did not recieve request until this afternoon.
BLD-Footing1/29/20162/1/20162/4/2016PPEND
DetailsDave Hannah
Rebar for columns & footings - Jason Phone #: ###-#### ok after s/i sign off
BLD-Foundation1/25/20161/25/20161/28/2016PPEND
DetailsDave Hannah
Jason Phone #: ###-####
BLD-Footing1/21/20161/22/20161/22/2016APEND
DetailsDave Hannah
Jason Phone #: ###-#### ok after spec/insp sign off
BLD-Foundation1/11/20161/11/20161/15/2016PPASS
DetailsDave Hannah
Jason-shear walll rebar and column rebar Phone #: ###-####
BLD-Footing1/6/20161/7/20161/7/2016APEND
DetailsDave Hannah
Jay-footings, calumns & Shear walls Phone #: ###-####
BLD-Foundation12/31/201512/31/20151/4/2016PPEND
DetailsDave Hannah
Rebar // Jason Phone #: ###-####
BLD-Foundation12/29/201512/30/201512/31/2015PPART
DetailsDave Hannah
Rebar // Jason Phone #: ###-#### ok after mti sign off
BLD-Foundation12/21/201512/22/201512/23/2015PPART
DetailsDave Hannah
rebar; Jason Phone #: ###-#### ok after mti does final on rebar