BLD-Framing/Rough-in | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Mike Jordan
|
|
|
Bert Phone #: ###-####
|
BLD-Energy code compliance | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Mike Jordan
|
|
|
Bert Phone #: ###-####
|
BLD-Framing/Rough-in | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Complete lateral bracing and airseal. Provide UL approved listings for through penetrations on 3hr fire barrier wall. (Pex)
|
BLD-Framing/Rough-in | 11/23/2016 | 11/23/2016 | 11/23/2016 | P | NR |
Mike Jordan
|
|
|
Bert Phone #: ###-####. Needs electrical rough in inspection.
|
BLD-Framing/Rough-in | 7/21/2016 | 7/22/2016 | 7/22/2016 | P | CANC |
Mike Jordan
|
|
|
Bert Phone #: ###-####
|
BLD-Wall Bracing | 7/21/2016 | 7/22/2016 | 7/22/2016 | P | PASS |
Mike Jordan
|
|
|
Shear // Bert Phone #: ###-####
|
BLD-Conference | 7/8/2016 | 7/8/2016 | 7/8/2016 | P | DONE |
Mike Jordan
|
|
|
Bert Phone #: ###-####
|
BLD-Wall Bracing | 7/8/2016 | 7/8/2016 | 7/8/2016 | P | PASS |
Mike Jordan
|
|
|
Bert Phone #: ###-####. Nailing on roof ok.
|
BLD-Foundation | 3/16/2016 | 3/17/2016 | 3/17/2016 | A | PASS |
Mike Jordan
|
|
|
Bert Phone #: ###-####. Interior footing for masonry wall ok.
|
BLD-Foundation | 2/23/2016 | 2/23/2016 | 2/23/2016 | P | CANC |
Mike Jordan
|
|
|
epoxy; Burt Phone #: ###-####
|
BLD-Foundation | 1/28/2016 | 1/29/2016 | 1/29/2016 | A | PASS |
Jim Sly
|
|
|
wall-###-#### Jim
|
BLD-Foundation | 1/27/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Jim Sly
|
|
|
Jim- ###-####
|
BLD-Footing | 1/27/2016 | 1/27/2016 | 1/27/2016 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Footing | 1/19/2016 | 1/20/2016 | 1/20/2016 | A | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Needs to install vertical rebar. Noted that their has been a resubmittal that involves footings.
|