BLD-Final | 1/18/2018 | 1/18/2018 | 1/19/2018 | P | PASS |
Dave Hannah
|
|
|
Nathan Phone #: ###-####
|
BLD-Final | 1/17/2018 | 1/18/2018 | 1/19/2018 | A | PASS |
Dave Hannah
|
|
|
Nathan Phone #: ###-####
|
BLD-Final | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
|
BLD-Other | 11/15/2017 | 11/16/2017 | 11/16/2017 | A | PASS |
Dave Hannah
|
|
|
Nathan-energy in the floor Phone #: ###-####
|
FIRE-Conference | 11/15/2017 | 11/16/2017 | 11/16/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete, mineral wool is installed over the foam that was exposed in the penthouse spaces.
|
BLD-Other | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | CANC |
Dave Hannah
|
|
|
Penthouse insulation - Nathan Phone #: ###-#### // cancelled per Nathan 9:39am 11/13 //leg
|
FIRE-Conference | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | CANC |
Jim Page
|
|
|
Penthouse insulation - Nathan Phone #: ###-#### // cancelled per Nathan 9:39am 11/13 //leg
|
FIRE-Final Inspection | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PART |
Troy Cobbley
|
|
|
TCO for 10th floor and all level 02 Rooms.
Scott Phone #: ###-####
|
BLD-Final | 10/27/2017 | 10/27/2017 | 10/30/2017 | P | PART |
Dave Hannah
|
|
|
Scott Phone #: ###-#### Requesting TCO for balance of project (10th floor and 02 rooms).ok to occ 10th
|
FIRE-Final Inspection | 10/27/2017 | 10/27/2017 | 10/27/2017 | P | CANC |
Troy Cobbley
|
|
|
Need to cancel due to time constraints. Scott is going to reschedule for monday.
Scott Phone #: ###-#### Requesting TCO for balance of project (10th floor and 02 rooms).
|
BLD-Final | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | PART |
Dave Hannah
|
|
|
Garage- TCO- Scott Phone #: ###-#### ok for temp occ on second floorparking garage
|
FIRE-Final Inspection | 10/16/2017 | 10/17/2017 | 10/17/2017 | A | PART |
Jim Page
|
|
|
Life fire safety inspection for level 2 TCO complete. Chemical placard will be placed on door of pool pump/chemical storage for swimming pool, placard will be verified at final BLD life fire safety inspection for project.
|
FIRE-Conference | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | DONE |
Jim Page
|
|
|
Walk through with Boise Fire department complete.
|
BLD-Final | 10/10/2017 | 10/10/2017 | 10/10/2017 | P | PEND |
Dave Hannah
|
|
|
Temp Occ to open hotel // Scott Phone #: ###-#### ok for temp occ on 1st floor and floors 3thru 9 ok for genral public
|
FIRE-Final Inspection | 10/10/2017 | 10/11/2017 | 10/10/2017 | A | PART |
Jim Page
|
|
|
Life fire safety for level 3 TCO complete, double key deadbolts on the northwest patio's off of capitol room will stay per conversation between Dave Hannah and I, signage will need to be installed reading "Door to remain unlocked while occupied". All construction debris will need to be removed from level 3 patio area before access of personnel other than construction is allowed. Gaurds will need to be installed around fire pit areas before final C of O.
|
BLD-Final | 10/6/2017 | 10/9/2017 | 10/9/2017 | P | PART |
Dave Hannah
|
|
|
Chandler Phone #: ###-#### ok for temp occ staff only
|
FIRE-Final Inspection | 10/6/2017 | 10/9/2017 | 10/9/2017 | A | PART |
Jim Page
|
|
|
Signature for life fire safety TCO requested has been completed for public occupancy excluding 2nd and 10th floors and also excluding the 3rd floor.
|
FIRE-Final Inspection | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | PART |
Jim Page
|
|
|
Defeciency list items for TCO requested levels, level 1 and levels 4 through 9 have been repaired with exception to the areas missing the photo luminescent tape on the handrails, Life fire safety inspection complete for TCO covered areas, TCO authorized for life fire safety per conversation with Ron Johnson.
|
BLD-Final | 10/3/2017 | 10/5/2017 | 10/5/2017 | P | NR |
Dave Hannah
|
|
|
George Phone #: ###-####
|
FIRE-Final Inspection | 10/4/2017 | 10/5/2017 | 10/5/2017 | A | FAIL |
Jim Page
|
|
|
Life fire safety deficiency list sent by email to Scott, Project Manager.
|
BLD-Ceiling Grid Inspection | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | PASS |
Dave Hannah
|
|
|
ceiling for common areas level 3 // George Phone #: ###-####
|
FIRE-Conference | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | DONE |
Jim Page
|
|
|
Fire conference for TCO discussion complete.
|
BLD-Framing/Rough-in | 9/7/2017 | 9/7/2017 | 9/7/2017 | P | PASS |
Dave Hannah
|
|
|
George, ceiling level 3 corridor and fitness room Phone #: ###-####
|
BLD-Framing/Rough-in | 8/30/2017 | 8/31/2017 | 8/31/2017 | A | PASS |
Dave Hannah
|
|
|
Nathan Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/30/2017 | 8/30/2017 | 8/30/2017 | P | PASS |
Dave Hannah
|
|
|
George Phone #: ###-####
|
FIRE-Conference | 8/23/2017 | 8/24/2017 | 8/24/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
BLD-Ceiling Grid Inspection | 8/17/2017 | 8/21/2017 | 8/23/2017 | P | PASS |
Dave Hannah
|
|
|
Nathan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PART |
Dave Hannah
|
|
|
Nate, overhead ceiling tile for 1st floor Phone #: ###-#### needs to fire stop wall pent
|
BLD-Other | 8/17/2017 | 8/17/2017 | 8/17/2017 | A | DONE |
Alexandra L. DeYoung
|
|
|
REFERENCE BLD15-02707 FOR INSPECTIONS PRIOR TO 8/16/17 (Concrete/Framing/Energy) -- ALD
|
BLD-Ceiling Grid Inspection | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | PART |
Brandon Shaw
|
|
|
02 Rooms- Level 3-10, 1 bedroom Kings, Soithwest corner
|
BLD-Other | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Brandon Shaw
|
|
|
Llinen shoot fire proofing, OK
|
BLD-Framing/Rough-in | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | PASS |
Dave Hannah
|
|
|
level 4 roof framing - James Phone #: ###-####
|
BLD-Concrete | | | 8/29/2016 | P | PART |
Mike Jordan
|
|
|
|
BLD-Conference | | | 8/19/2016 | P | DEFR |
Mike Jordan
|
|
|
|
BLD-Concrete | | | 8/16/2016 | P | DEFR |
Mike Jordan
|
|
|
|
BLD-Concrete | | | 8/9/2016 | P | PEND |
Dave Hannah
|
|
|
|
BLD-Concrete | | | 8/5/2016 | P | PEND |
Dave Hannah
|
|
|
|
BLD-Concrete | | | 7/28/2016 | P | PEND |
Dave Hannah
|
|
|
|
BLD-Concrete | 7/13/2016 | 7/13/2016 | 7/14/2016 | P | PEND |
Dave Hannah
|
|
|
Level 4 south PT deck reinforcement. Structural Engineer has been onsite and has reviewed. SI has been on site and is scheduled for the pour. Concrete pour scheduled for 9:30 pm tonight. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | PEND |
Dave Hannah
|
|
|
Walls at elevator core level 3-4, misc. columns. concrete scheduled for 10 am Saturday. MTI has been on site for periodic special inspections and is also scheduled. Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 6/14/2016 | 6/14/2016 | 6/27/2016 | A | PASS |
Dave Hannah
|
|
|
Foundation wall stair core 2 level 2-3. MTI has been onsite for progress inspections and is scheduled. Concrete scheduled for 10 am tomorrow.
PT deck level 3 pour 1 is ready. Concrete scheduled for Wednesday 9 pm Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 6/24/2016 | 6/24/2016 | 6/24/2016 | A | PART |
Mike Jordan
|
|
|
PT suspended slab Pour #2 level 3. SI has been doing periodic inspections all week. SI will be onsite today and for pour. Concrete scheduled for 10 pm tonight. Phone #: ###-#### Inspection requested via web by Jim Williams. Work in progress. ok after special inspection has signed off.
|
BLD-Conference | 6/1/2016 | 6/2/2016 | 6/14/2016 | A | PEND |
Dave Hannah
|
|
|
stair core 3 level 2.Concrete scheduled for 3pm. SI scheduled and will be onsite. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 5/12/2016 | 5/12/2016 | 5/12/2016 | A | PASS |
Dave Hannah
|
|
|
pool wall level 2. PT suspended slab level 2 pour 3. Concrete scheduled for 2 am 5/13 for PT deck. Friday afternoon 2 pm. Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 4/28/2016 | 4/28/2016 | 5/5/2016 | P | PART |
Dave Hannah
|
|
|
PT suspended concrete slab level 2 pour 2. Concrete scheduled for 2 am 4/29. Elevator core wall reinforcement. 100''- 116'' elevation. MTI has been on site and conducted inspected. SS is scheduled to be on site for pours. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 5/3/2016 | 5/3/2016 | 5/4/2016 | P | PEND |
Dave Hannah
|
|
|
Stair core 1 from elevation 116'' to 127'' rebar, Concrete scheduled for 5/4 2pm. Would like to begin buttoning up forms this afternoon Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 4/12/2016 | 4/12/2016 | 4/14/2016 | P | PEND |
Dave Hannah
|
|
|
Suspended PT level 2 deck Grid lines A-H 6.5-10 pour 1 of three. Structural engineer and MTI have been onsite and reviewed. Concrete scheduled for 3 am tomorrow.
FR 16x20 footing Grids 1-H Concrete schedules 4 pm today Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 3/9/2016 | 3/10/2016 | 3/11/2016 | A | PEND |
Dave Hannah
|
|
|
FS footing grid line C 1.9 and 3, Columns grid C-4 , D.5-5 and B-6 Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 3/7/2016 | 3/7/2016 | 3/10/2016 | P | PASS |
Dave Hannah
|
|
|
Stair 3 core walls , 4 columns grids H-7,C.5 6-7,C-5 2 pm concrete. SI has already reviewed rebar and will be on site. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 2/29/2016 | 3/1/2016 | 3/2/2016 | A | PASS |
Dave Hannah
|
|
|
Perimeter foundation XY grid SW. Concrete pier Grid 5;6 at grid A. Concrete columns grid C.5 6.3-7. and grid H -7.Concrete scheduled for 2 pm SI has been scheduled and already inspected column reinforcement prior to form placement Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 2/18/2016 | 2/18/2016 | 2/19/2016 | A | PEND |
Dave Hannah
|
|
|
Footings Grid line A-1-3.5: Grid line 1 A-C. Concrete scheduled for 11:00 am. SI scheduled and will be onsite for pour. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 2/15/2016 | 2/16/2016 | 2/18/2016 | P | PEND |
Dave Hannah
|
|
|
Foundation reinforcement stair 1 grid line F 9-10, Column reinforcement grid lines 6-8 A-H Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Conference | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | DEFR |
Mike Jordan
|
|
|
FS footings and continuous exterior footings Grid line A 4-6.5; Exterior continuous footings. Grid line H 4-6.5 Concrete scheduled 8am SI has already reviewed rebar and is scheduled onsite for tomorrows pour. Phone #: ###-#### Inspection requested via web by Jim Williams. Special inspection has approved. Concrete placement in progress. Special inspector on site.
|
BLD-Foundation | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PEND |
Dave Hannah
|
|
|
Grid line A 7-10, Grid line H 7-10, Tower crane base foundation. 10 am Friday concrete scheduled. Phone #: ###-#### Inspection requested via web by Jim Williams ok after s/i sign off
|
BLD-Foundation | 1/29/2016 | 1/29/2016 | 2/1/2016 | A | PASS |
Dave Hannah
|
|
|
3'' Foundation wall Grid line 10- B.8-H; Grid line H 8.8-10. Concrete scheduled for 2 pm. Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 1/27/2016 | 1/28/2016 | 1/28/2016 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams Inspection of Select large footing pads for columns.........OK pending MTI special inspections, tests and approvals.
|